Scope and capacity
DayOne Batam NVIDIA DSX AI Factory Campus is a physical 360 MW DSX campus developed with DayOne. Exact Kabil or Nongsa placement is not established by the DSX sources. DayOne Batam NVIDIA DSX AI Factory Campus is located in Batam, KR, ID and is a data center campus in preconstruction status.
Headline: 360 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (2)
Planned campus capacity · 360 MW
Planned / design or future potential · DayOne Batam NVIDIA DSX AI Factory Campus (Project)
Claim 33836 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- NVIDIA unlocks AI compute at scale with capital partners
NVIDIA · Document date: Jul 1, 2026 · Corroborating
Source reference: SRC-1901 · Company announcement · Recorded authority: Party primary
Source URL
https://blogs.nvidia.com/blog/nvidia-unlocks-ai-compute-at-scale-capital-partners-to-power-ai-infrastructure-buildout/
https://blogs.nvidia.com/blog/nvidia-unlocks-ai-compute-at-scale-capital-partners-to-power-ai-infrastructure-buildout/
- Firmus to build 170,000 GPU AI Factory campus with NVIDIA for global AI natives
Firmus Technologies · Document date: Jun 29, 2026 · Primary
Source reference: SRC-1900 · Company announcement · Recorded authority: Party primary
Source URL
https://firmus.co/newsroom/firmus-to-build-170-000-gpu-ai-factor-y-campus-with-nvidia-for-global-ai-natives
https://firmus.co/newsroom/firmus-to-build-170-000-gpu-ai-factor-y-campus-with-nvidia-for-global-ai-natives
- BP Batam welcomes Firmus Technologies expansion
BP Batam · Document date: Jun 29, 2026 · Corroborating
Source reference: SRC-1902 · Government record · Recorded authority: Official primary
Source URL
https://bpbatam.go.id/bp-batam-sambut-baik-ekspansi-firmus-technologies-perkuat-posisi-batam-sebagai-hub-infrastruktur-ai-regional/
https://bpbatam.go.id/bp-batam-sambut-baik-ekspansi-firmus-technologies-perkuat-posisi-batam-sebagai-hub-infrastruktur-ai-regional/
Physical campus developer · DayOne
Actual · DayOne Batam NVIDIA DSX AI Factory Campus (Project)
Claim 33837 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Firmus to build 170,000 GPU AI Factory campus with NVIDIA for global AI natives
Firmus Technologies · Document date: Jun 29, 2026 · Primary
Source reference: SRC-1900 · Company announcement · Recorded authority: Party primary
Source URL
https://firmus.co/newsroom/firmus-to-build-170-000-gpu-ai-factor-y-campus-with-nvidia-for-global-ai-natives
https://firmus.co/newsroom/firmus-to-build-170-000-gpu-ai-factor-y-campus-with-nvidia-for-global-ai-natives
Counterparties and capital
BP Batam · Government authority · CMP-0915
DayOne Data Centers · Developer · CMP-0071
Firmus Technologies · Customer · CMP-0914
PLN Batam · Utility provider · CMP-0916
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.