Cartis diligence evidence schedule
DATA4 PAR03 Nozay AI Campus
PRJ-0398 · Site · Nozay, Île-de-France, France
Record last updated Oct 28, 2026
Scope and capacity
PAR03 is DATA4's 22-hectare Nozay AI campus, redesigned in 2025 around 250 MW of power capacity and a EUR 2 billion investment envelope. DATA4 PAR03 Nozay AI Campus is located in Nozay, Ile-de-France, FR and is a data center campus in preconstruction status.
Headline: 250 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (10)
Current planned power capacity · 250 MW
Planned / design or future potential · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36719 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
- DATA4 Paris-Saclay campus profile
DATA4 · Document date: Not stated · Corroborating
Source reference: SRC-2061 · Recorded authority: Party primary
Source URL
https://www.data4group.com/en/data-center-in-paris-france/
https://www.data4group.com/en/data-center-in-paris-france/
Current investment plan · €2 billion
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36721 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
Site area · 22 hectares
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36722 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
- DATA4 Paris-Saclay campus profile
DATA4 · Document date: Not stated · Corroborating
Source reference: SRC-2061 · Recorded authority: Party primary
Source URL
https://www.data4group.com/en/data-center-in-paris-france/
https://www.data4group.com/en/data-center-in-paris-france/
Site address · 7 Route de Villejust, 91620 Nozay
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36723 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 Paris-Saclay campus profile
DATA4 · Document date: Not stated · Primary
Source reference: SRC-2061 · Recorded authority: Party primary
Source URL
https://www.data4group.com/en/data-center-in-paris-france/
https://www.data4group.com/en/data-center-in-paris-france/
Former nokia site · True
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36724 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 launches Escaudain and describes Paris brownfield hub
DATA4 · Document date: Jun 12, 2026 · Corroborating
Source reference: SRC-2062 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/en/news-data4/in-northern-france-data4-launches-its-largest-data-center-campus-to-support-europes-ai-growth/
https://www.data4group.com/en/news-data4/in-northern-france-data4-launches-its-largest-data-center-campus-to-support-europes-ai-growth/
- DATA4 announces third Paris campus
Data Center Dynamics · Document date: Apr 5, 2023 · Primary
Source reference: SRC-2063 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/data4-announces-plans-for-third-paris-campus/
https://www.datacenterdynamics.com/en/news/data4-announces-plans-for-third-paris-campus/
Designed GPU capacity nearly · 200,000 GPUs
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36727 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
Designed compute power · 4 million petaFLOPS
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36728 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
Heat reuse to nozay ecodistrict planned · True
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36729 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
- DATA4 announces new PAR03 campus in France
DATA4 · Document date: May 19, 2023 · Corroborating
Source reference: SRC-2060 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/en/news-data4/data4-annonces-new-data-center-campus-in-france/
https://www.data4group.com/en/news-data4/data4-annonces-new-data-center-campus-in-france/
Daily full time professionals claimed over · 1,000 people
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36731 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- DATA4 unveils 250 MW PAR03 AI campus redesign
DATA4 · Document date: May 16, 2025 · Primary
Source reference: SRC-2059 · Company announcement · Recorded authority: Party primary
Source URL
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
https://www.data4group.com/wp-content/uploads/2025/06/CP-PAR03-ENG.pdf
Brookfield platform owner · True
Actual · DATA4 PAR03 Nozay AI Campus (Project)
Claim 36734 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Brookfield Infrastructure corporate profile November 2023
Brookfield Infrastructure · Document date: Nov 1, 2023 · Corroborating
Source reference: SRC-2066 · Recorded authority: Party primary
Source URL
https://bip.brookfield.com/sites/bip-brookfield-ir/files/2023-11/corporate-profile-november-2023.pdf
https://bip.brookfield.com/sites/bip-brookfield-ir/files/2023-11/corporate-profile-november-2023.pdf
- Brookfield Infrastructure Q2 2023 letter
Brookfield Infrastructure · Document date: Aug 3, 2023 · Primary
Source reference: SRC-2064 · Recorded authority: Party primary
Source URL
https://bip.brookfield.com/bip/reports-filings/letters-unitholders/bip-q2-2023-letter-unitholders
https://bip.brookfield.com/bip/reports-filings/letters-unitholders/bip-q2-2023-letter-unitholders
Counterparties and capital
Brookfield Asset Management · Investor · CMP-0743
Commune of Nozay · Government authority · CMP-0988
DATA4 Group · Developer · CMP-0078
RTE · Utility provider · CMP-0130
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.