About DATA4 Frankfurt–Hanau Campus
DATA4 broke ground on its first German campus in Hanau in September 2025. The former military site is planned for a 180 MW electrical envelope and more than €2 billion of investment.
Capacity
Operating capacity—An operating IT-capacity figure has not been publicly disclosed.
Design180 MWDesign · Hanau phased full campus
Development
3 phases · 4 milestonesGrossauheim remediation and preparationUnder Construction
Former barracks remediation and recycled-material scope.
Hanau initial constructionUnder Construction
Historical first-module 2025 target is not treated as achieved.
1 building
Hanau phased full campusPlanned
Planned campus power and schedule, not current IT capacity.
Jul 21, 2022
P3 acquires former barracks site
CompletedFeb 15, 2023
DATA4 announces Hanau campus
CompletedSep 15, 2025
DATA4 Hanau groundbreaking
CompletedJan 1, 2032
Full Hanau buildout target
ForecastInfrastructure
Electric GridPlanned Or Represented
180 MW
Available/reserved campus electricity, not current IT load.
Electric GridPlanned Or Represented
Rating and energization date unresolved.
Onsite GenerationPlanned Or Represented
Technology, fuel and approvals unresolved.
Heat ReusePlanned Or Represented
Intent only; no commissioned heat delivery.
Renewable Energy SupplyPlanned Or Represented
100 percent
Future operating-energy target, not current achieved supply.
Project map
0 of 1 project point mappedInfrastructure facts
5
Mapped records
1
Capacity figures
2
No map point available
Power & interconnection: 3Generation & storage: 1Cooling & water: 1
Facts & sources
Published claims and their source links.
Current StatusUnder construction after groundbreakingActual
Under construction after groundbreaking
Site Area25 hectaresActual
25 hectares
AddressDepotstraße, 63457 HanauActual
Depotstraße, 63457 Hanau
Campus Electrical Envelope180 MWDesign
180 MW
Current Announced InvestmentMore than €2 billionTransaction Scope
More than €2 billion
Site HistoryFormer Großauheim U.S. military barracksActual
Former Großauheim U.S. military barracks
Predecessor SponsorP3 Logistic ParksActual
P3 Logistic Parks
Full Buildout Target2032Forecast
2032
SubstationPlannedDesign
Planned
Combined Heat And Power PlantPlannedDesign
Planned
Waste Heat ReuseIntended for Hanau district heatingDesign
Intended for Hanau district heating
Energy Target100% Decarbonized source electricityForecast
100% Decarbonized source electricity
Platform OwnerBrookfield InfrastructureActual
Brookfield Infrastructure