DATA4 Frankfurt–Hanau Campus
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
DATA4 broke ground on its first German campus in Hanau in September 2025. The former military site is planned for a 180 MW electrical envelope and more than €2 billion of investment.
Capacity
Campus electrical envelope
Planned / design or future potential180 MW
Hanau phased full campus · Phase
Phase scope; not a whole-site figure
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Former barracks remediation and recycled-material scope.
1 building
Historical first-module 2025 target is not treated as achieved.
Planned campus power and schedule, not current IT capacity.
Milestones (4)
Jul 21, 2022 · Recorded actual event
Completed · Land acquired
Source not linkedFeb 15, 2023 · Recorded actual event
Completed · Announced
Source not linkedSep 15, 2025 · Recorded actual event
Completed · Construction started
Source not linked2032 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Investor
Sources by role
Investor (1)
- AXA IM Alts agrees to sale of DATA4 to Brookfield Infrastructure · Apr 11, 2023 · Primary
Operator
Sources by role
Operator (1)
- DATA4 lays the foundation stone for its first data center in Germany · Sep 15, 2025 · Corroborating
Operator (1)
- DATA4 sets its sights on Germany with more than one billion euros of investment · Feb 15, 2023 · Primary
Operator (1)
- Our campus of data centers in Germany · Corroborating
Owner
Sources by role
Owner (1)
- P3 Logistic Parks takes over barracks site to develop green data center campus in Hanau · Jul 21, 2022 · Primary
Other participants (2)
Government authority
Sources by role
Government authority (1)
- DATA4 lays the foundation stone for its first data center in Germany · Sep 15, 2025 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
€2,000,000,000Sep 15, 2025
Source says more than €2B; no debt/equity or site financing allocation disclosed.
Parties & sources
Brookfield Infrastructure (Other) · DATA4 Group (Sponsor)
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (5)
Planned or represented
180 MW
Available/reserved campus electricity, not current IT load.
Planned or represented
Rating and energization date unresolved.
Planned or represented
Technology, fuel and approvals unresolved.
Planned or represented
Intent only; no commissioned heat delivery.
Planned or represented
100 percent
Future operating-energy target, not current achieved supply.
Project map
Grading · Documented
Former Großauheim barracks remediation and campus development
City of Hanau
Sep 15, 2025
Sources (2)
- DATA4 lays the foundation stone for its first data center in Germany · Sep 15, 2025 · Corroborating
- DATA4 sets its sights on Germany with more than one billion euros of investment · Feb 15, 2023 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.