CyrusOne SAT5–SAT6 San Antonio Data Center Campus
PRJ-0855 · Site · San Antonio, Texas, United States
Captured 2026-09-06T04:13:58.385Z · Record last updated 2026-08-30
SHA-256: cd73439e4d983c695e7a75ebcf74609e3aab6617b27a640a7feaa2f47742bbb0
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
CyrusOne SAT5–SAT6 San Antonio Data Center Campus, also known as CyrusOne SAT5–SAT6, is a partially operational data center campus in San Antonio, TX, US associated with CyrusOne. 175,000 square feet; 33 MW total IT capacity across the current development. Two-facility San Antonio complex with water-free cooling and metro/cloud interconnection.
Headline: 33 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Location Context · CyrusOne SAT5–SAT6 | San Antonio | TX | US
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 62642 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Lifecycle Status · Operational
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 62643 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Reported Capacity · 33 MW
design · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 62644 · Review: Approved · Claim date: Not published
Headline treatment: Separate claim, not added to the headline
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Capacity Basis · CyrusOne publishes 33 MW of critical IT capacity for this record boundary.
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 62645 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Location Context · CyrusOne SAT5–SAT6 | San Antonio | TX | US
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97388 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Lifecycle Status · Operating
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97389 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Reported Capacity · 33 MW
Planned / design or future potential · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97390 · Review: Approved · Claim date: Not published
Headline treatment: Separate claim, not added to the headline
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Capacity Basis · 33 MW facility or campus design capacity.
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97391 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Project Boundary · CyrusOne SAT5–SAT6
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97393 · Review: Approved · Claim date: Not published
- CyrusOne current global data-center portfolio
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Location Context · San Antonio, TX, US
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97394 · Review: Approved · Claim date: Not published
- CyrusOne current global data-center portfolio
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Lifecycle Status · Operating
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97395 · Review: Approved · Claim date: Not published
- CyrusOne current global data-center portfolio
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Development Detail · Two facility San Antonio complex; 175,000 square feet of technical IT space; 33 MW IT capacity across the current development.
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97396 · Review: Approved · Claim date: Not published
- CyrusOne current global data-center portfolio
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Capacity Basis · 33 MW facility or campus design capacity.
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 97397 · Review: Approved · Claim date: Not published
- CyrusOne current global data-center portfolio
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Location Context · CyrusOne SAT5–SAT6 | San Antonio | TX | US
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104362 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Lifecycle Status · Partially operational
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104363 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Reported Capacity · 33 MW
Planned / design or future potential · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104364 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Capacity Basis · 33 MW facility or campus IT design capacity.
actual · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104365 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Campus It Design · 33 MW
Planned / design or future potential · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104366 · Review: Approved · Claim date: Not published
Headline treatment: Separate claim, not added to the headline
- CyrusOne CyrusOne SAT5–SAT6 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/san-antonio-sat5-sat6
Building Area · 175,000 square feet
design · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104367 · Review: Approved · Claim date: Not published
- CyrusOne sustainability reporting
CyrusOne · Document date: 2026-08-30 · Primary
https://www.cyrusone.com/resources/sustainability-report
Sat6 Project Area · 132,070 square feet
design · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104368 · Review: Approved · Claim date: Not published
- CyrusOne sustainability reporting
CyrusOne · Document date: 2026-08-30 · Primary
https://www.cyrusone.com/resources/sustainability-report
Sat6 Registered Cost · $50,000,000
transaction scope · CyrusOne SAT5–SAT6 San Antonio Data Center Campus (project)
Claim 104369 · Review: Approved · Claim date: Not published
- CyrusOne sustainability reporting
CyrusOne · Document date: 2026-08-30 · Primary
https://www.cyrusone.com/resources/sustainability-report
Counterparties and capital
CyrusOne · Developer · CMP-0172
$50,000,000 · 2021-04-29
TDLR estimate for SAT VI, not campus-wide investment.
CyrusOne (Borrower)
Financing record 204; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.