CyrusOne PAR1 Paris Data Center Campus

Wissous, Île-de-France, FrancePartially operational
Evidence
Planned critical IT
27 MW
Updated
Oct 28, 2026

On April 2, 2026, the Versailles administrative appeal court rejected the challenge to CyrusOne’s November 2021 environmental registration at Wissous. This regulatory decision does not establish commissioning of PAR1’s expansion or approval of every future phase. CyrusOne PAR1 Paris Data Center Campus, also known as CyrusOne PAR1, is a partially operational data center campus in Wissous, IDF, FR associated with CyrusOne. Six planned data halls across three phases; 27 MW total design; 4.5 MW identified as operating on the current profile. Phased Paris-region campus with dual redundant power, closed-loop cooling and renewable-energy sourcing. 4.5 MW is the current operating-phase design. The separate 27 MW figure is the six-hall, three-phase full-build plan.

Capacity

Reported capacity

Design

27 MW

Source

Reported capacity

Actual

4.5 MW

Source

Reported capacity

Planned / design or future potential

4.5 MW

Source

Current phase design

Design

4.5 MW

Source

Full build design

Forecast

27 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Three-phase PAR1 developmentPartially operational

3 buildings

4.5 MW operating + 6.9 MW non-operational + 15.6 MW authorization-stage = 27 MW full design.

Operating facility and documented expansionPartially operational

4.5 MW is the current operating-phase design. The separate 27 MW figure is the six-hall, three-phase full-build plan.

Milestones (3)
Phase 1 operating at 4.5 MW

Aug 29, 2026 · Recorded actual event

Completed · Commercial operation

Source not linked
Phase 3 remains authorization-stage

Aug 29, 2026 · Recorded actual event

Completed · Permit filed

Source not linked
Current profile distinguishes 4.5 MW operating phase from 27 MW full build

Aug 30, 2026 · Recorded actual event

Completed · Capacity revised

Source not linked

Participants

CyrusOne

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

CyrusOne PAR1 | Wissous | Île de-France | FR

Source

Location context

Actual

CyrusOne PAR1 | Wissous | Île de-France | FR

Source

Technical area

Design

10,396 square metres

Source

Location context

Actual

CyrusOne PAR1 | Wissous | IDF | FR

Source

Development phases

Design

3 phases

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

CyrusOne publishes 27 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

4.5 MW is the current operating Phase 1 IT boundary. The remaining 22.5 MW belongs to non operational or authorization stage phases within the 27 MW full design.

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

4.5 MW is the current operating phase design. The separate 27 MW figure is the six hall, three phase full build plan.

Source

Planned data halls

Forecast

6 data halls

Source

Infrastructure & permits

Technical details (5)
Electric grid

Energized

Resilient utility supply, efficient closed-loop cooling, carrier-neutral connectivity and heat-reuse readiness.

Cooling system

Operational

CyrusOne describes closed-loop or air-cooled systems; the profile does not infer facility water use beyond the cited site specification.

Electric grid

Energized

Phased Paris-region campus with dual redundant power, closed-loop cooling and renewable-energy sourcing.

Cooling system

Operational

Cooling and efficiency claims remain limited to source-defined designs; no delivered load or water use is inferred.

Electric grid

Planned or represented

4.5 MW current design

Current phase is distinct from the 27 MW full-build plan.

Public-source research. Plans may change. See Evidence for sources and qualifications.