Cartis diligence evidence schedule

CyrusOne FRA7 Frankfurt Westside

PRJ-0043 · Site · Stroofstraße / FRANKFURT WESTSIDE, Frankfurt-Griesheim, Hesse, Germany

Record last updated Oct 28, 2026

Scope and capacity

CyrusOne's FRA7 is under construction inside FRANKFURT WESTSIDE. Its current design is 81 MW of IT capacity across nine halls in two buildings, with up to 40 MW of future waste heat available to the wider development.

Headline: 81 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project status · Under construction; first building topped out

Actual · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6002 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 1, 2024

  1. CyrusOne Tops Out Latest Frankfurt Data Center in Germany

    Data Center Dynamics · Document date: Feb 9, 2026 · Corroborating

    Source reference: SRC-0339 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/cyrusone-tops-out-latest-frankfurt-data-center-in-germany/

  2. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Site area · 63,000 sq m

Actual · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6003 · Recorded claim type: Actual · Review: Approved · Claim date: Sep 8, 2023

  1. BEOS AG and CyrusOne Reach Key Milestone in Solidifying Strategic Partnership in FRANKFURT WESTSIDE

    BEOS AG · Document date: Apr 18, 2024 · Corroborating

    Source reference: SRC-0337 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.beos.net/newsroom/pressemitteilungen/beos-ag-und-cyrusone-erreichen-entscheidenden-meilenstein-zur-festigung-der-strategischen-partnerschaft-in-der-frankfurt-westside

  2. CyrusOne Announces New Frankfurt Data Center with BEOS and Swiss Life Asset Managers

    CyrusOne · Document date: Sep 8, 2023 · Primary

    Source reference: SRC-0335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-announces-new-frankfurt-data-center-with-beos-and-swiss-life-asset-managers

  3. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Corroborating

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Parent development area · 73 hectares

Actual · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6004 · Recorded claim type: Actual · Review: Approved · Claim date: Sep 8, 2023

  1. BEOS AG and CyrusOne Reach Key Milestone in Solidifying Strategic Partnership in FRANKFURT WESTSIDE

    BEOS AG · Document date: Apr 18, 2024 · Corroborating

    Source reference: SRC-0337 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.beos.net/newsroom/pressemitteilungen/beos-ag-und-cyrusone-erreichen-entscheidenden-meilenstein-zur-festigung-der-strategischen-partnerschaft-in-der-frankfurt-westside

  2. CyrusOne Announces New Frankfurt Data Center with BEOS and Swiss Life Asset Managers

    CyrusOne · Document date: Sep 8, 2023 · Primary

    Source reference: SRC-0335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-announces-new-frankfurt-data-center-with-beos-and-swiss-life-asset-managers

  3. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Corroborating

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Total IT capacity · 81 MW

Planned / design or future potential · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6005 · Recorded claim type: Design · Review: Approved · Claim date: Sep 8, 2023

Headline treatment: Selected headline

  1. CyrusOne Announces New Frankfurt Data Center with BEOS and Swiss Life Asset Managers

    CyrusOne · Document date: Sep 8, 2023 · Corroborating

    Source reference: SRC-0335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-announces-new-frankfurt-data-center-with-beos-and-swiss-life-asset-managers

  2. Frankfurt, Germany: FRA7

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0334 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/data-centers/emea/frankfurt-germany-fra7

  3. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Corroborating

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Building count · 2 buildings

Design · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6006 · Recorded claim type: Design · Review: Approved · Claim date: Sep 8, 2023

  1. CyrusOne Announces New Frankfurt Data Center with BEOS and Swiss Life Asset Managers

    CyrusOne · Document date: Sep 8, 2023 · Corroborating

    Source reference: SRC-0335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-announces-new-frankfurt-data-center-with-beos-and-swiss-life-asset-managers

  2. Frankfurt, Germany: FRA7

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0334 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/data-centers/emea/frankfurt-germany-fra7

Data hall count · 9 halls

Design · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6007 · Recorded claim type: Design · Review: Approved · Claim date: Sep 8, 2023

  1. CyrusOne Tops Out Latest Frankfurt Data Center in Germany

    Data Center Dynamics · Document date: Feb 9, 2026 · Corroborating

    Source reference: SRC-0339 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/cyrusone-tops-out-latest-frankfurt-data-center-in-germany/

  2. CyrusOne Announces New Frankfurt Data Center with BEOS and Swiss Life Asset Managers

    CyrusOne · Document date: Sep 8, 2023 · Primary

    Source reference: SRC-0335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-announces-new-frankfurt-data-center-with-beos-and-swiss-life-asset-managers

Technical space · 25,266 sq m

Design · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6008 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. Frankfurt, Germany: FRA7

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0334 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/data-centers/emea/frankfurt-germany-fra7

Designed IT load · 54 MW

Design · First building (Phase)

Claim 6009 · Recorded claim type: Design · Review: Approved · Claim date: Feb 9, 2026

Headline treatment: Phase scope; not a whole-site figure

  1. CyrusOne Tops Out Latest Frankfurt Data Center in Germany

    Data Center Dynamics · Document date: Feb 9, 2026 · Primary

    Source reference: SRC-0339 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/cyrusone-tops-out-latest-frankfurt-data-center-in-germany/

Designed IT load · 9 MW

Design · Initial 9 MW hall/phase (Phase)

Claim 6010 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Phase scope; not a whole-site figure

  1. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Anticipated investment · €>1000000000

Transaction scope · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6012 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Not stated

  1. CyrusOne Tops Out Latest Frankfurt Data Center in Germany

    Data Center Dynamics · Document date: Feb 9, 2026 · Corroborating

    Source reference: SRC-0339 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/cyrusone-tops-out-latest-frankfurt-data-center-in-germany/

  2. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Waste heat export potential · 40 MW thermal

Forecast · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6013 · Recorded claim type: Forecast · Review: Approved · Claim date: Sep 8, 2023

  1. BEOS AG and CyrusOne Reach Key Milestone in Solidifying Strategic Partnership in FRANKFURT WESTSIDE

    BEOS AG · Document date: Apr 18, 2024 · Corroborating

    Source reference: SRC-0337 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.beos.net/newsroom/pressemitteilungen/beos-ag-und-cyrusone-erreichen-entscheidenden-meilenstein-zur-festigung-der-strategischen-partnerschaft-in-der-frankfurt-westside

  2. CyrusOne Announces New Frankfurt Data Center with BEOS and Swiss Life Asset Managers

    CyrusOne · Document date: Sep 8, 2023 · Primary

    Source reference: SRC-0335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-announces-new-frankfurt-data-center-with-beos-and-swiss-life-asset-managers

  3. CyrusOne Breaks Ground on Most Recent Data Center in Germany

    CyrusOne · Document date: Not stated · Corroborating

    Source reference: SRC-0336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/media-coverage-press-releases/cyrusone-breaks-ground-on-most-recent-data-center-in-germany-representing-one-of-the-largest-waste-heat-utilization-projects-in-europe

Utility supply design · 150 MVA

Design · CyrusOne FRA7 Frankfurt Westside (Project)

Claim 6014 · Recorded claim type: Design · Review: Approved · Claim date: Apr 18, 2024

  1. BEOS AG and CyrusOne Reach Key Milestone in Solidifying Strategic Partnership in FRANKFURT WESTSIDE

    BEOS AG · Document date: Apr 18, 2024 · Primary

    Source reference: SRC-0337 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.beos.net/newsroom/pressemitteilungen/beos-ag-und-cyrusone-erreichen-entscheidenden-meilenstein-zur-festigung-der-strategischen-partnerschaft-in-der-frankfurt-westside

Expanded total IT plan · 126 MW

Planned / design or future potential · E.ON local-generation expansion concept (Phase)

Claim 6016 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Phase scope; not a whole-site figure

  1. CyrusOne and E.ON Announce Strategic Partnership to Overcome Data Center Grid Capacity Constraints

    CyrusOne · Document date: Not stated · Primary

    Source reference: SRC-0338 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.cyrusone.com/resources/press-releases/cyrusone-and-e.on-announce-strategic-partnership-to-overcome-data-center-grid-capacity-constraints-for-customers-in-europe

Counterparties and capital

BEOS AG · Developer · CMP-0204

CyrusOne · Owner · CMP-0203

E.ON Energy Infrastructure Solutions · Utility provider · CMP-0206

State of Hesse · Government authority · CMP-0208

Swiss Life Asset Managers Deutschland GmbH · Investor · CMP-0205

TSL · Contractor · CMP-0207

Investment commitment

Amount not disclosed · Not stated

Ultimate anticipated FRA7 investment; current spend and capital stack undisclosed. Source wording: anticipated investment exceeds EUR 1 billion.

CyrusOne (Sponsor)

Financing record 34; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.