Scope and capacity
CyrusOne AMS1 Amsterdam Data Center Campus, also known as CyrusOne AMS1, is a data center project in Halfweg, North Holland, NL associated with CyrusOne. Purpose-built campus; 29,350 square metres of technical space at full build; 54 MW IT load. Amsterdam-region build-to-suit campus designed for resilient power, scalable halls and carrier-neutral connectivity. 54 MW is the operator-published future facility or full-build design boundary.
Headline: 54 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Location context · CyrusOne AMS1 | Halfweg | North Holland | NL
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 61851 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Lifecycle status · Construction
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 61852 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Reported capacity · 54 MW
Design · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 61853 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Capacity basis · CyrusOne publishes 54 MW of critical IT capacity for this record boundary.
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 61854 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Location context · CyrusOne AMS1 | Halfweg | North Holland | NL
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97105 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Lifecycle status · Construction
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97106 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Reported capacity · 54 MW
Planned / design or future potential · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97107 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Capacity basis · 54 MW is the operator published future facility or full build design boundary.
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97108 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne AMS1 Data Sheet
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3437 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
https://www.cyrusone.com/hubfs/CyrusOne/C1_AMS1_DataSheet_SD.pdf?hsLang=en
Project boundary · CyrusOne AMS1
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97110 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- State of the Dutch Data Centers 2023
Dutch Data Center Association · Document date: Jun 14, 2023 · Primary
Source reference: SRC-5329 · News report · Recorded authority: Secondary
Source URL
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
Location context · Halfweg, North Holland, NL
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97111 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- State of the Dutch Data Centers 2023
Dutch Data Center Association · Document date: Jun 14, 2023 · Primary
Source reference: SRC-5329 · News report · Recorded authority: Secondary
Source URL
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
Lifecycle status · Construction
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97112 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- State of the Dutch Data Centers 2023
Dutch Data Center Association · Document date: Jun 14, 2023 · Primary
Source reference: SRC-5329 · News report · Recorded authority: Secondary
Source URL
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
Development detail · Purpose built campus; 29,350 square metres of technical space at full build; 54 MW IT load.
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97113 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- State of the Dutch Data Centers 2023
Dutch Data Center Association · Document date: Jun 14, 2023 · Primary
Source reference: SRC-5329 · News report · Recorded authority: Secondary
Source URL
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
Capacity basis · 54 MW is the operator published future facility or full build design boundary.
Actual · CyrusOne AMS1 Amsterdam Data Center Campus (Project)
Claim 97114 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- State of the Dutch Data Centers 2023
Dutch Data Center Association · Document date: Jun 14, 2023 · Primary
Source reference: SRC-5329 · News report · Recorded authority: Secondary
Source URL
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
https://www.dutchdatacenters.nl/wp-content/uploads/lana-downloads/2023/06/SODD-23_Final_140623.pdf
Counterparties and capital
CyrusOne · Developer · CMP-0172