Cartis diligence evidence schedule
Crusoe Tallgrass Wyoming
PRJ-1085 · Site · Cheyenne, Wyoming, United States
Record last updated Oct 28, 2026
Scope and capacity
Crusoe and Tallgrass announced a Wyoming AI-data-center and energy campus near Cheyenne with an initial 1.8 GW plan and a longer-term expansion opportunity. Later reporting tied the development to Google and a larger 2.7 GW concept, but schedule and customer scope have shifted, making the earlier Cartis headline materially ambiguous. The available public sources do not establish a single project-scoped capacity figure.8 GW pending definitive customer and permit evidence. Onsite generation, carbon-management infrastructure, transmission and delivery phases remain under development.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Location context · Crusoe Tallgrass Wyoming | Cheyenne | Wyoming | US
Actual · Crusoe Tallgrass Wyoming (Project)
Claim 70312 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Crusoe Tallgrass Wyoming public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4008 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/wyoming/
https://dcmap.us/states/wyoming/
Lifecycle status · Delayed
Actual · Crusoe Tallgrass Wyoming (Project)
Claim 70313 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Crusoe Tallgrass Wyoming public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4008 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/wyoming/
https://dcmap.us/states/wyoming/
Capacity basis · 2,700 MW future full build site capacity; not measured operating IT load.
Actual · Crusoe Tallgrass Wyoming (Project)
Claim 70315 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Crusoe Tallgrass Wyoming public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4008 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/wyoming/
https://dcmap.us/states/wyoming/
Location context · Crusoe Tallgrass Wyoming | Cheyenne | Wyoming | US
Actual · Crusoe Tallgrass Wyoming (Project)
Claim 74493 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Crusoe Tallgrass Wyoming public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4008 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/wyoming/
https://dcmap.us/states/wyoming/
Lifecycle status · Delayed
Actual · Crusoe Tallgrass Wyoming (Project)
Claim 74494 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Crusoe Tallgrass Wyoming public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4008 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/wyoming/
https://dcmap.us/states/wyoming/
Customer identity · Google association reported; definitive phase scope remains unsettled
Actual · Crusoe Tallgrass Wyoming (Project)
Claim 74499 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Tallgrass and Crusoe announce Wyoming AI campus
Tallgrass · Document date: Jul 23, 2025 · Primary
Source reference: SRC-4232 · Company announcement · Recorded authority: Party primary
Source URL
https://www.tallgrass.com/newsroom/press-releases/Crusoe
https://www.tallgrass.com/newsroom/press-releases/Crusoe
Counterparties and capital
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.