Cartis diligence evidence schedule
Christopher M. Crane Clean Energy Center Restart
PRJ-0112 · Energy asset · Londonderry Township / Middletown, Pennsylvania, United States
Captured 2026-09-06T04:13:38.277Z · Record last updated 2026-08-24
SHA-256: 148fe16fbdc4641b90561048e3c95f874ed81044b8dc11c1b37407bb2271e1e0
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Constellation is restarting the 835-MW former Three Mile Island Unit 1 under a 20-year Microsoft power-purchase agreement, subject to nuclear and grid approvals. Christopher M. Crane Clean Energy Center Restart is in Londonderry Township / Middletown, PA, US and is a energy asset restart with construction status.
Headline: 835 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Nameplate Capacity · 835 MW
Planned / design or future potential · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12717 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- NRC public meeting on possible Crane restart
U.S. Nuclear Regulatory Commission · Document date: 2026-07-14 · Corroborating
https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-019-i-a.pdf - FERC waiver advances Three Mile Island restart
Utility Dive · Document date: 2026-06-03 · Corroborating
https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/ - FERC order granting interconnection waiver for Crane
Federal Energy Regulatory Commission · Document date: 2026-06-01 · Corroborating
https://www.rtoinsider.com/wp-content/uploads/2026/06/FERC-ER26-2028-000-Crane-Eddystone-Waiver.pdf - Crane Clean Energy Center license-amendment applications
U.S. Nuclear Regulatory Commission / Federal Register · Document date: 2026-02-24 · Corroborating
https://www.federalregister.gov/documents/2026/02/24/2026-03626/constellation-energy-generation-llc-christopher-m-crane-clean-energy-center-applications-for - Energy Department closes loan to restart Pennsylvania nuclear plant
U.S. Department of Energy · Document date: 2025-11-19 · Corroborating
https://www.energy.gov/articles/energy-department-closes-loan-restart-nuclear-power-plant-pennsylvania - Constellation commits to Pennsylvania energy investments
Constellation Energy · Document date: 2025-07-15 · Corroborating
https://www.constellationenergy.com/news/2025/constellation-commits-to-billions-of-dollars-in-energy-investments-at-inaugural-pennsylvania-energy-and-innovation-summit.html - Constellation to launch Crane Clean Energy Center
Constellation Energy · Document date: 2024-09-20 · Primary
https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html - Crane Clean Energy Center current project page
Constellation Energy · Document date: Not published · Corroborating
https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html - Crane restart project
U.S. Department of Energy · Document date: Not published · Corroborating
https://www.energy.gov/edf/crane-restart
Ppa Term · 20 years
Source report · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12718 · Review: Approved · Claim date: Not published
- Constellation to launch Crane Clean Energy Center
Constellation Energy · Document date: 2024-09-20 · Primary
https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html
Doe Guaranteed Loan · $1,000,000,000
Source report · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12719 · Review: Approved · Claim date: Not published
- Energy Department closes loan to restart Pennsylvania nuclear plant
U.S. Department of Energy · Document date: 2025-11-19 · Primary
https://www.energy.gov/articles/energy-department-closes-loan-restart-nuclear-power-plant-pennsylvania - Crane restart project
U.S. Department of Energy · Document date: Not published · Corroborating
https://www.energy.gov/edf/crane-restart
Restart Cost Estimate · $1,600,000,000
Source report · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12720 · Review: Approved · Claim date: Not published
- FERC waiver advances Three Mile Island restart
Utility Dive · Document date: 2026-06-03 · Primary
https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/
Transferred Interconnection Rights · 760 MW
Source report · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12721 · Review: Approved · Claim date: Not published
- FERC waiver advances Three Mile Island restart
Utility Dive · Document date: 2026-06-03 · Corroborating
https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/ - FERC order granting interconnection waiver for Crane
Federal Energy Regulatory Commission · Document date: 2026-06-01 · Primary
https://www.rtoinsider.com/wp-content/uploads/2026/06/FERC-ER26-2028-000-Crane-Eddystone-Waiver.pdf
Target Commercial Generation Year · 2027
Planned / design or future potential · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12722 · Review: Approved · Claim date: Not published
- FERC waiver advances Three Mile Island restart
Utility Dive · Document date: 2026-06-03 · Corroborating
https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/ - Constellation commits to Pennsylvania energy investments
Constellation Energy · Document date: 2025-07-15 · Primary
https://www.constellationenergy.com/news/2025/constellation-commits-to-billions-of-dollars-in-energy-investments-at-inaugural-pennsylvania-energy-and-innovation-summit.html
Construction Jobs · 3,400 jobs
Source report · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12724 · Review: Approved · Claim date: Not published
- Constellation to launch Crane Clean Energy Center
Constellation Energy · Document date: 2024-09-20 · Primary
https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html - Crane Clean Energy Center current project page
Constellation Energy · Document date: Not published · Corroborating
https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html
Nrc Restart Approval · Pending
actual · Christopher M. Crane Clean Energy Center Restart (project)
Claim 12725 · Review: Approved · Claim date: Not published
- NRC public meeting on possible Crane restart
U.S. Nuclear Regulatory Commission · Document date: 2026-07-14 · Corroborating
https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-019-i-a.pdf - Crane Clean Energy Center license-amendment applications
U.S. Nuclear Regulatory Commission / Federal Register · Document date: 2026-02-24 · Primary
https://www.federalregister.gov/documents/2026/02/24/2026-03626/constellation-energy-generation-llc-christopher-m-crane-clean-energy-center-applications-for
Counterparties and capital
Constellation Energy Generation, LLC · Owner · CMP-0418
Federal Energy Regulatory Commission · Government Authority · CMP-0422
Federal Financing Bank · Lender · CMP-0420
Microsoft · Customer · CMP-0017
PJM Interconnection · Utility Provider · CMP-0423
U.S. Department of Energy, Energy Dominance Financing · Government Authority · CMP-0419
U.S. Nuclear Regulatory Commission · Government Authority · CMP-0421
$1,000,000,000 · 2025-11-18
Federal Financing Bank loan guaranteed through DOE program; partially finances restart.
Constellation Energy Generation, LLC (Borrower) · Federal Financing Bank (Lender) · U.S. Department of Energy, Energy Dominance Financing (Other)
Financing record 54; claim-specific source links appear in the exhibit sources where published.
$1,600,000,000 · 2026-06-03
Reported restart-cost estimate; not an executed debt or equity facility.
Financing record 55; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.