Christopher M. Crane Clean Energy Center Restart

PRJ-0112 · Energy asset · Londonderry Township / Middletown, Pennsylvania, United States

Captured 2026-09-06T04:13:38.277Z · Record last updated 2026-08-24

SHA-256: 148fe16fbdc4641b90561048e3c95f874ed81044b8dc11c1b37407bb2271e1e0

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Constellation is restarting the 835-MW former Three Mile Island Unit 1 under a 20-year Microsoft power-purchase agreement, subject to nuclear and grid approvals. Christopher M. Crane Clean Energy Center Restart is in Londonderry Township / Middletown, PA, US and is a energy asset restart with construction status.

Headline: 835 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Nameplate Capacity · 835 MW

Planned / design or future potential · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12717 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. NRC public meeting on possible Crane restart

    U.S. Nuclear Regulatory Commission · Document date: 2026-07-14 · Corroborating

    https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-019-i-a.pdf
  2. FERC waiver advances Three Mile Island restart

    Utility Dive · Document date: 2026-06-03 · Corroborating

    https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/
  3. FERC order granting interconnection waiver for Crane

    Federal Energy Regulatory Commission · Document date: 2026-06-01 · Corroborating

    https://www.rtoinsider.com/wp-content/uploads/2026/06/FERC-ER26-2028-000-Crane-Eddystone-Waiver.pdf
  4. Crane Clean Energy Center license-amendment applications

    U.S. Nuclear Regulatory Commission / Federal Register · Document date: 2026-02-24 · Corroborating

    https://www.federalregister.gov/documents/2026/02/24/2026-03626/constellation-energy-generation-llc-christopher-m-crane-clean-energy-center-applications-for
  5. Energy Department closes loan to restart Pennsylvania nuclear plant

    U.S. Department of Energy · Document date: 2025-11-19 · Corroborating

    https://www.energy.gov/articles/energy-department-closes-loan-restart-nuclear-power-plant-pennsylvania
  6. Constellation commits to Pennsylvania energy investments

    Constellation Energy · Document date: 2025-07-15 · Corroborating

    https://www.constellationenergy.com/news/2025/constellation-commits-to-billions-of-dollars-in-energy-investments-at-inaugural-pennsylvania-energy-and-innovation-summit.html
  7. Constellation to launch Crane Clean Energy Center

    Constellation Energy · Document date: 2024-09-20 · Primary

    https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html
  8. Crane Clean Energy Center current project page

    Constellation Energy · Document date: Not published · Corroborating

    https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html
  9. Crane restart project

    U.S. Department of Energy · Document date: Not published · Corroborating

    https://www.energy.gov/edf/crane-restart

Ppa Term · 20 years

Source report · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12718 · Review: Approved · Claim date: Not published

  1. Constellation to launch Crane Clean Energy Center

    Constellation Energy · Document date: 2024-09-20 · Primary

    https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html

Doe Guaranteed Loan · $1,000,000,000

Source report · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12719 · Review: Approved · Claim date: Not published

  1. Energy Department closes loan to restart Pennsylvania nuclear plant

    U.S. Department of Energy · Document date: 2025-11-19 · Primary

    https://www.energy.gov/articles/energy-department-closes-loan-restart-nuclear-power-plant-pennsylvania
  2. Crane restart project

    U.S. Department of Energy · Document date: Not published · Corroborating

    https://www.energy.gov/edf/crane-restart

Restart Cost Estimate · $1,600,000,000

Source report · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12720 · Review: Approved · Claim date: Not published

  1. FERC waiver advances Three Mile Island restart

    Utility Dive · Document date: 2026-06-03 · Primary

    https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/

Transferred Interconnection Rights · 760 MW

Source report · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12721 · Review: Approved · Claim date: Not published

  1. FERC waiver advances Three Mile Island restart

    Utility Dive · Document date: 2026-06-03 · Corroborating

    https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/
  2. FERC order granting interconnection waiver for Crane

    Federal Energy Regulatory Commission · Document date: 2026-06-01 · Primary

    https://www.rtoinsider.com/wp-content/uploads/2026/06/FERC-ER26-2028-000-Crane-Eddystone-Waiver.pdf

Target Commercial Generation Year · 2027

Planned / design or future potential · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12722 · Review: Approved · Claim date: Not published

  1. FERC waiver advances Three Mile Island restart

    Utility Dive · Document date: 2026-06-03 · Corroborating

    https://www.utilitydive.com/news/constellation-three-mile-island-crane-nuclear-ferc-waiver/821836/
  2. Constellation commits to Pennsylvania energy investments

    Constellation Energy · Document date: 2025-07-15 · Primary

    https://www.constellationenergy.com/news/2025/constellation-commits-to-billions-of-dollars-in-energy-investments-at-inaugural-pennsylvania-energy-and-innovation-summit.html

Construction Jobs · 3,400 jobs

Source report · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12724 · Review: Approved · Claim date: Not published

  1. Constellation to launch Crane Clean Energy Center

    Constellation Energy · Document date: 2024-09-20 · Primary

    https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html
  2. Crane Clean Energy Center current project page

    Constellation Energy · Document date: Not published · Corroborating

    https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html

Nrc Restart Approval · Pending

actual · Christopher M. Crane Clean Energy Center Restart (project)

Claim 12725 · Review: Approved · Claim date: Not published

  1. NRC public meeting on possible Crane restart

    U.S. Nuclear Regulatory Commission · Document date: 2026-07-14 · Corroborating

    https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-019-i-a.pdf
  2. Crane Clean Energy Center license-amendment applications

    U.S. Nuclear Regulatory Commission / Federal Register · Document date: 2026-02-24 · Primary

    https://www.federalregister.gov/documents/2026/02/24/2026-03626/constellation-energy-generation-llc-christopher-m-crane-clean-energy-center-applications-for

Counterparties and capital

Constellation Energy Generation, LLC · Owner · CMP-0418

Federal Energy Regulatory Commission · Government Authority · CMP-0422

Federal Financing Bank · Lender · CMP-0420

Microsoft · Customer · CMP-0017

PJM Interconnection · Utility Provider · CMP-0423

U.S. Department of Energy, Energy Dominance Financing · Government Authority · CMP-0419

U.S. Nuclear Regulatory Commission · Government Authority · CMP-0421

Debt Financing

$1,000,000,000 · 2025-11-18

Federal Financing Bank loan guaranteed through DOE program; partially finances restart.

Constellation Energy Generation, LLC (Borrower) · Federal Financing Bank (Lender) · U.S. Department of Energy, Energy Dominance Financing (Other)

Financing record 54; claim-specific source links appear in the exhibit sources where published.

Investment Commitment

$1,600,000,000 · 2026-06-03

Reported restart-cost estimate; not an executed debt or equity facility.

Financing record 55; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.