Cartis diligence evidence schedule

CoreWeave Lancaster AI Data Center

PRJ-0705 · Site · Lancaster area, Pennsylvania, United States

Record last updated Oct 28, 2026

Scope and capacity

CoreWeave announced a new purpose-built AI data center in Lancaster County, Pennsylvania. The initial facility is planned for 100 MW with room to expand to 300 MW. CoreWeave, Chirisa Technology Parks, Machine Investment Group is associated with the development in Lancaster area, Lancaster County, PA, US. The disclosed development scope includes 100 MW initial planned capacity; up to 300 MW expansion; up to US$6 billion equipment commitment. Power and physical infrastructure include purpose-built AI data-center infrastructure in the Mid-Atlantic market. CoreWeave states the initial Lancaster data center will be 100 MW. CoreWeave announced an equipment commitment exceeding $6 billion for the initial Lancaster development.

Headline: 100 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · CoreWeave AI data center | Lancaster County | Pennsylvania

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 57960 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Lifecycle status · Preconstruction

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 57961 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Reported capacity · 100 MW

Planned / design or future potential · CoreWeave Lancaster AI Data Center (Project)

Claim 57962 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Capacity basis · CoreWeave states the initial Lancaster data center will be 100 MW.

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 57963 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Location context · CoreWeave AI data center | Lancaster County | Pennsylvania

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111407 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Lifecycle status · Preconstruction

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111408 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Reported capacity · 100 MW

Planned / design or future potential · CoreWeave Lancaster AI Data Center (Project)

Claim 111409 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Capacity basis · CoreWeave states the initial Lancaster data center will be 100 MW.

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111410 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Development scale · 100 MW initial planned capacity

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111427 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Turner and CoreWeave Lancaster announcement

    Turner Construction · Document date: Jul 21, 2025 · Corroborating

    Source reference: SRC-6248 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.hochtief.com/fileadmin/aktuelles_medien/press-releases/250721_Turner_CoreWeave_Data_Center.pdf

  2. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Development milestone · Up to 300 MW expansion

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111428 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Turner and CoreWeave Lancaster announcement

    Turner Construction · Document date: Jul 21, 2025 · Corroborating

    Source reference: SRC-6248 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.hochtief.com/fileadmin/aktuelles_medien/press-releases/250721_Turner_CoreWeave_Data_Center.pdf

  2. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Power arrangement · Up to US$6 billion equipment commitment.

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111429 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Turner and CoreWeave Lancaster announcement

    Turner Construction · Document date: Jul 21, 2025 · Corroborating

    Source reference: SRC-6248 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.hochtief.com/fileadmin/aktuelles_medien/press-releases/250721_Turner_CoreWeave_Data_Center.pdf

  2. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Site configuration · CoreWeave AI data center | Lancaster County | Pennsylvania

Actual · CoreWeave Lancaster AI Data Center (Project)

Claim 111430 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Turner and CoreWeave Lancaster announcement

    Turner Construction · Document date: Jul 21, 2025 · Corroborating

    Source reference: SRC-6248 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.hochtief.com/fileadmin/aktuelles_medien/press-releases/250721_Turner_CoreWeave_Data_Center.pdf

  2. CoreWeave announces AI infrastructure commitment in Pennsylvania

    CoreWeave · Document date: Jul 15, 2025 · Primary

    Source reference: SRC-3168 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx

Counterparties and capital

Chirisa Technology Parks · Developer · CMP-1445

CoreWeave · Tenant · CMP-0099

Machine Investment Group · Developer · CMP-0778