CoreSite SV9 is an operating 228,000-square-foot data center at 2915 Stender Way, Santa Clara, CA. The facility is part of CoreSite’s Silicon Valley interconnection platform, linking customers to carrier, cloud and peering services through the Open Cloud Exchange. Its published 34 MW specification describes facility design capacity.

Headline: 34 MW Facility design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Reported capacity · 34 MW operating facility design capacity

Facility electrical / design capacity · CoreSite SV9 Santa Clara Data Center (Project)

Claim 156662 · Recorded claim type: Actual · Review: Approved · Claim date: Sep 1, 2026

Headline treatment: Selected headline

  1. SV9 data center

    CoreSite · Document date: Sep 1, 2026 · Primary

    Source reference: SRC-7668 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coresite.com/data-center/sv9-santa-clara-ca

  2. Silicon Valley data centers

    CoreSite · Document date: Sep 1, 2026 · Corroborating

    Source reference: SRC-7669 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coresite.com/data-center-locations/silicon-valley

Building area · 228,000 sq. ft.

Actual · CoreSite SV9 Santa Clara Data Center (Project)

Claim 156663 · Recorded claim type: Actual · Review: Approved · Claim date: Sep 1, 2026

  1. SV9 data center

    CoreSite · Document date: Sep 1, 2026 · Primary

    Source reference: SRC-7668 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coresite.com/data-center/sv9-santa-clara-ca

  2. Silicon Valley data centers

    CoreSite · Document date: Sep 1, 2026 · Corroborating

    Source reference: SRC-7669 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coresite.com/data-center-locations/silicon-valley

Counterparties and capital

CoreSite · Operator · CMP-1652