Skip to content
← Return to profile

Cartis diligence evidence schedule

Cologix Johnstown AI Data Center Campus

PRJ-1172 · Site · Johnstown, Ohio, United States

Record last updated Oct 28, 2026

Scope and capacity

Cologix is developing an AI-ready data-center campus near Johnstown in Licking County after acquiring land for a new Central Ohio site. The planned campus is designed for up to 800 MW and extends Cologix’s regional platform beyond its operating Columbus interconnection facilities. Building count, delivery sequence and initial energization remain to be announced.

Headline: 800 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Reported capacity · 800 MW planned campus design capacity

Planned / design or future potential · Cologix Johnstown AI Data Center Campus (Project)

Claim 154722 · Recorded claim type: Forecast · Review: Approved · Claim date: Nov 20, 2024

Headline treatment: Selected headline

  1. Cologix Columbus data-center platform

    Cologix · Document date: Aug 31, 2026 · Corroborating

    Source reference: SRC-7420 · Company announcement · Recorded authority: Party primary

    Source URL

    https://cologix.com/data-centers/columbus/

  2. Cologix acquires land for 800 MW Johnstown campus

    Cologix · Document date: Nov 20, 2024 · Primary

    Source reference: SRC-7419 · Company announcement · Recorded authority: Party primary

    Source URL

    https://cologix.com/news/cologix-expands-central-ohio-footprint-with-land-acquisition-for-new-ai-ready-800mw-data-center-campus/

Planned capacity · 800 MW

Planned / design or future potential · Cologix Johnstown AI Data Center Campus (Project)

Claim 154723 · Recorded claim type: Forecast · Review: Approved · Claim date: Nov 20, 2024

Headline treatment: Separate claim, not added to the headline

  1. Cologix Columbus data-center platform

    Cologix · Document date: Aug 31, 2026 · Corroborating

    Source reference: SRC-7420 · Company announcement · Recorded authority: Party primary

    Source URL

    https://cologix.com/data-centers/columbus/

  2. Cologix acquires land for 800 MW Johnstown campus

    Cologix · Document date: Nov 20, 2024 · Primary

    Source reference: SRC-7419 · Company announcement · Recorded authority: Party primary

    Source URL

    https://cologix.com/news/cologix-expands-central-ohio-footprint-with-land-acquisition-for-new-ai-ready-800mw-data-center-campus/

Counterparties and capital

Cologix, Inc. · Operator · CMP-1651

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.