Cartis diligence evidence schedule

CleanCore–Cerebras Minnesota AI Data Center

PRJ-0700 · Site · Minnesota, United States

Record last updated Oct 28, 2026

Scope and capacity

CleanCore disclosed a Minnesota AI data-center transaction associated with Cerebras. The baseline lease covers 40 MW of critical IT capacity within a facility with 55 MW of utility capacity. CleanCore Solutions, Cerebras Systems is associated with the development in Minnesota location undisclosed, MN, US. The disclosed development scope includes 40 MW baseline critical IT lease; 55 MW utility capacity; location undisclosed. Power and physical infrastructure include aI infrastructure planned around an existing utility-capacity envelope. The disclosed baseline lease covers 40 MW of critical IT capacity. The ten-year colocation agreement has an initial stated value of approximately $800 million; the sponsor expects to own nearly 80% of the project.

Headline: 40 MW Contracted

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · CleanCore AI facility | Minnesota | precise boundary undisclosed

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 57940 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Lifecycle status · Preconstruction

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 57941 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Reported capacity · 40 MW

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 57942 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Capacity basis · The disclosed baseline lease covers 40 MW of critical IT capacity.

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 57943 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Location context · CleanCore AI facility | Minnesota | precise boundary undisclosed

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111367 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Lifecycle status · Preconstruction

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111368 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Reported capacity · 40 MW

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111369 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Capacity basis · The disclosed baseline lease covers 40 MW of critical IT capacity.

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111370 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

Development scale · 40 MW baseline critical IT lease

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111387 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

  2. Cerebras Q2 2026 results

    Cerebras Systems · Document date: Aug 12, 2026 · Corroborating

    Source reference: SRC-6240 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/2021728/000162828026056186/cbrsannouncesfinancialresu.htm

Development milestone · 55 MW utility capacity

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111388 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

  2. Cerebras Q2 2026 results

    Cerebras Systems · Document date: Aug 12, 2026 · Corroborating

    Source reference: SRC-6240 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/2021728/000162828026056186/cbrsannouncesfinancialresu.htm

Power arrangement · Location undisclosed.

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111389 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

  2. Cerebras Q2 2026 results

    Cerebras Systems · Document date: Aug 12, 2026 · Corroborating

    Source reference: SRC-6240 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/2021728/000162828026056186/cbrsannouncesfinancialresu.htm

Site configuration · CleanCore AI facility | Minnesota | precise boundary undisclosed

Actual · CleanCore–Cerebras Minnesota AI Data Center (Project)

Claim 111390 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore reports Minnesota AI data center transaction

    CleanCore Solutions · Document date: Aug 14, 2026 · Primary

    Source reference: SRC-3162 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026082561/ea0299459-8k_cleancore.htm

  2. Cerebras Q2 2026 results

    Cerebras Systems · Document date: Aug 12, 2026 · Corroborating

    Source reference: SRC-6240 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/2021728/000162828026056186/cbrsannouncesfinancialresu.htm

Counterparties and capital

Cerebras Systems · Tenant · CMP-1441

CleanCore Solutions · Developer · CMP-1440

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.