Centersquare EWR2 is an operating carrier-neutral data center on the Weehawken waterfront, less than ten miles from New York’s financial district. The 199,110-square-foot facility has 45.7 MW of utility capacity, 20.7 MW of UPS capacity and 31 MW of generator capacity, with 28 network providers. Utility and backup ratings are kept separate from customer IT load.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Operating Weehawken colocation facility.
Participants
Operator
Sources by role
Operator (1)
- New York and New Jersey data centers · Aug 31, 2026 · Corroborating
Operator (1)
- EWR2 facility specifications · Oct 1, 2025 · Primary
Site & development
Infrastructure & permits
Technical details (3)
Operational
45.7 MW
Utility capacity.
Operational
31 MW
Generator capacity.
Operational
28 providers
Carrier-neutral network ecosystem.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
Operating · Secaucus, New Jersey, United States
Shared participant: Centersquare · Same market: New Jersey, United States
Compare in a collection