Cartis diligence evidence schedule
CDC Marsden Park Campus
PRJ-0029 · Site · Marsden Park, Sydney, New South Wales, Australia
Record last updated Oct 28, 2026
Scope and capacity
CDC's current Marsden Park operator timeline, checked October 28, 2026, forecasts staged commissioning and handover from September 2027 to December 2029, rather than a single campus opening date. CDC's Marsden Park campus is under construction in Sydney's Blacktown area and has development approval for six data-center buildings with 504 MW of planned ICT capacity.
Headline: 1,000 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (11)
Project status · Under construction
Actual · CDC Marsden Park Campus (Project)
Claim 3868 · Recorded claim type: Actual · Review: Approved · Claim date: Oct 25, 2024
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
- Sydney data-centre locations
CDC Data Centres · Document date: Not stated · Corroborating
Source reference: SRC-0214 · Fact sheet · Recorded authority: Party primary
Source URL
https://cdc.com.au/locations/sydney/
https://cdc.com.au/locations/sydney/
- Infratil newsletter — April 2025 CDC site visit
Infratil · Document date: Not stated · Corroborating
Source reference: SRC-0218 · Company announcement · Recorded authority: Party primary
Source URL
https://infratil.com/news/infratil-newsletter-april-2025-cdc-site-visit/
https://infratil.com/news/infratil-newsletter-april-2025-cdc-site-visit/
Planned ict capacity · 504 MW
Planned / design or future potential · CDC Marsden Park Campus (Project)
Claim 3869 · Recorded claim type: Forecast · Review: Approved · Claim date: Oct 25, 2024
Headline treatment: Separate claim, not added to the headline
- Marsden Park Data Centre SSD-70889211
NSW Planning Portal · Document date: Nov 27, 2025 · Corroborating
Source reference: SRC-0215 · Government record · Recorded authority: Official primary
Source URL
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
Planned building count · 6 building
Forecast · CDC Marsden Park Campus (Project)
Claim 3870 · Recorded claim type: Forecast · Review: Approved · Claim date: Oct 25, 2024
- Marsden Park Data Centre SSD-70889211
NSW Planning Portal · Document date: Nov 27, 2025 · Corroborating
Source reference: SRC-0215 · Government record · Recorded authority: Official primary
Source URL
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
Data halls per building · 24 hall per building
Design · CDC Marsden Park Campus (Project)
Claim 3871 · Recorded claim type: Design · Review: Approved · Claim date: Oct 25, 2024
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
Site area · 20.1 hectare
Actual · CDC Marsden Park Campus (Project)
Claim 3872 · Recorded claim type: Actual · Review: Approved · Claim date: Oct 25, 2024
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
Onsite substation capacity · 720 MVA
Actual · CDC Marsden Park Campus (Project)
Claim 3873 · Recorded claim type: Actual · Review: Approved · Claim date: Oct 25, 2024
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
Ssd application id · SSD-70889211
Actual · CDC Marsden Park Campus (Project)
Claim 3875 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 27, 2025
- Marsden Park Data Centre SSD-70889211
NSW Planning Portal · Document date: Nov 27, 2025 · Primary
Source reference: SRC-0215 · Government record · Recorded authority: Official primary
Source URL
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
Ssd status · Approved
Actual · CDC Marsden Park Campus (Project)
Claim 3876 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 27, 2025
- Marsden Park Data Centre SSD-70889211
NSW Planning Portal · Document date: Nov 27, 2025 · Primary
Source reference: SRC-0215 · Government record · Recorded authority: Official primary
Source URL
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
https://www.planningportal.nsw.gov.au/major-projects/projects/marsden-park-data-centre
Construction jobs · >10000 job
Reported rounded · CDC Marsden Park Campus (Project)
Claim 3877 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Oct 25, 2024
- CDC Data Centres breaks ground on new development in Marsden Park industrial precinct
CDC Data Centres · Document date: Oct 25, 2024 · Primary
Source reference: SRC-0213 · Company announcement · Recorded authority: Party primary
Source URL
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
https://cdc.com.au/resources/news/cdc-data-centres-breaks-ground-on-new-state-of-the-art-data-centre-development-in-marsden-park-industrial-precinct/
Current operator capacity description · >504 MW
Planned / design or future potential · CDC Marsden Park Campus (Project)
Claim 3878 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Sydney data-centre locations
CDC Data Centres · Document date: Not stated · Primary
Source reference: SRC-0214 · Fact sheet · Recorded authority: Party primary
Source URL
https://cdc.com.au/locations/sydney/
https://cdc.com.au/locations/sydney/
Future scalability · 1,000 MW
Planned / design or future potential · CDC Marsden Park Campus (Project)
Claim 3879 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Sydney data-centre locations
CDC Data Centres · Document date: Not stated · Primary
Source reference: SRC-0214 · Fact sheet · Recorded authority: Party primary
Source URL
https://cdc.com.au/locations/sydney/
https://cdc.com.au/locations/sydney/
Counterparties and capital
Blacktown City Council · Government authority · CMP-0133
CDC Data Centres · Owner · CMP-0131
Commonwealth Superannuation Corporation · Investor · CMP-0136
Future Fund · Investor · CMP-0135
Infratil · Investor · CMP-0134
NSW Department of Planning, Housing and Infrastructure · Government authority · CMP-0132
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.