Campus AI France
- Planned critical IT
- 1,400 MW
- Updated
- Oct 28, 2026
Campus AI's operator reports prefectural authorization in July 2026 and entry into works in September 2026. Its June 2026 announcement also identified Mistral as an anchor customer; these are development milestones, not confirmation that the campus is operating. Campus AI is an AI infrastructure development progressing into works in Seine-et-Marne backed by MGX, Bpifrance, Mistral AI and NVIDIA. The €8.5 billion program targets 1.4 GW at full development, with the first phase planned for 2028 and RTE grid infrastructure forming part of the delivery program.
Capacity
Capacity basis
Planned / design or future potential1,400 MW planned full development AI campus capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Campus AI France: Development program.
Milestones (2)
May 19, 2025 · Event timing type not established
In progress · Announced
Source not linkedDate not disclosed · Event timing type not established
In progress · Status changed
Source not linkedParticipants
Investor
Sources by role
Investor (1)
- MGX, Bpifrance, Mistral AI and NVIDIA launch joint venture for AI campus in France · May 19, 2025 · Primary
Investor
Sources by role
Investor (1)
- MGX, Bpifrance, Mistral AI and NVIDIA launch joint venture for AI campus in France · May 19, 2025 · Primary
Tenant
Sources by role
Tenant (1)
- MGX, Bpifrance, Mistral AI and NVIDIA launch joint venture for AI campus in France · May 19, 2025 · Primary
Other participants (1)
Contractor
Sources by role
Contractor (1)
- MGX, Bpifrance, Mistral AI and NVIDIA launch joint venture for AI campus in France · May 19, 2025 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Development scale
ActualCampus AI is a planned AI infrastructure development in Seine et-Marne backed by MGX, Bpifrance, Mistral AI and NVIDIA. The €8.5 billion program targets 1.4 GW at full development, with the first phase planned for 2028 and RTE grid infrastructure forming part of the delivery program.
SourceInfrastructure
ActualThe €8.5 billion program targets 1.4 GW at full development, with the first phase planned for 2028 and RTE grid infrastructure forming part of the delivery program.
SourceFinancing records
Investment commitment
€8,500,000,000May 19, 2025
Investment program for Campus AI.
Parties & sources
MGX (Sponsor)
Sources (2)
- MGX, Bpifrance, Mistral AI and NVIDIA launch joint venture for AI campus in France · May 19, 2025
- Choose France 2025 investment program · May 19, 2025
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Planned or represented
1,400 MW
1,400 MW planned full-development AI campus capacity
Planned or represented
The €8.5 billion program targets 1.4 GW at full development, with the first phase planned for 2028 and RTE grid infrastructure forming part of the delivery program.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.