Data center siteSite record

Brookfield Strängnäs AI Center

Strängnäs, Södermanland, SwedenPreconstruction
Capacity
750 MW
Planned / design
Lead participant
Brookfield Asset Management
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Brookfield Strängnäs AI Center

Brookfield's proposed Strängnäs AI center could scale from a 300 MW base plan to a 750 MW total envelope, but land completion and development remain contingent on adequate power. Brookfield Strängnäs AI Center is located in Strängnäs, Södermanland, SE and is a data center campus in preconstruction status. Participants include Brookfield Asset Management as developer, Strängnäs Municipality as landowner, Svenska kraftnät as utility, Vattenfall as utility. Published specifications include 300 MW of planned capacity, 750 MW of planned capacity. Development comprises Base campus plan (proposed), Expansion to 750 MW total campus envelope (proposed). Key milestones include Municipality announces conditional land path (2025-06-04) and Power availability identified as material project gate (2025-11-20). electricity service — 750 MW: Power must be secured within the municipal diligence window; 750 MW is the proposed campus-total envelope, not connected capacity. Permitting includes existing detailed plan / industrial and technical uses for Gorsingeberget development area (approved context).

Program relationships

1 linked

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential300 MWActual · Brookfield Strängnäs AI Center
Future Potential750 MWActual · Brookfield Strängnäs AI Center

Development

2 phases · 2 milestones
Base campus planAnnounced Or Preconstruction

Original/base plan; no building permits or construction start.

Expansion to 750 MW total campus envelopeAnnounced Or Preconstruction

750 MW is the campus total after expansion, not an incremental phase capacity.

Jun 4, 2025
Municipality announces conditional land path
Completed
Nov 20, 2025
Power availability identified as material project gate
Completed

Infrastructure

Utility ServiceUnknown

750 MW

Power must be secured within the municipal diligence window; 750 MW is the proposed campus-total envelope, not connected capacity.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

11 facts
Planned Base Capacity
300 MW
Actual
Planned Total Capacity Up To
750 MW
Actual
Additional Land Area Approximately
350,000 square metres
Actual
Conditional Land Price
525 SEK million
Actual
Land Reversion If Conditions Fail
True
Actual
Power Diligence Window
2 years
Actual
Planned Buildout Duration
10 years minimum
Actual
Planned Buildout Duration Upper
15 years
Actual
Planned Permanent Jobs Over
1,000 jobs
Actual
Planned Construction Jobs
2,000 jobs
Actual
Existing Industrial Zoning Context
True
Actual