BlockchAIn CLT-01 AI Data Center Campus
- Utility capacity
- 65 MW
- Updated
- Oct 28, 2026
AIB Data Centers' October 7, 2026 SEC-filed disclosure confirms a 12-year Nebius agreement for 50 MW of critical IT capacity at CLT1, following the September 30 announcement. This is contracted future AI capacity, not an operating upgrade; it remains distinct from the site's 65 MW utility agreement. AIB Data Centers, formerly BlockchAIn Digital Infrastructure, is converting its CLT-01 campus in South Carolina from cryptocurrency hosting toward AI and high-performance-computing use. A 15-year utility agreement provides 65 MW of contract demand, but no definitive long-term AI tenant lease had been executed as of August 13, 2026. Earlier profile references placed the development in the Charlotte region, NC; the issuer describes the CLT-01 site as being in South Carolina, and the legacy location fields require separate reconciliation. The disclosed development scope includes 65 MW contracted utility demand; existing 40 MW energized infrastructure; bitcoin-hosting operations de-energized in June 2026; definitive AI tenant lease not yet executed as of August 13, 2026, before the later Nebius agreement. Power and physical infrastructure include existing 34.5 kV onsite distribution can support the contracted utility load without major electrical upgrades. A 15-year electric-service agreement covers 65 MW of utility load.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Project-wide phase for BlockchAIn CLT-01 AI Data Center Campus; capacity class is utility service.
Milestones (2)
May 27, 2026 · Recorded actual event
Completed · Announced
Source not linkedDate not disclosed · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- BlockchAIn executes 65 MW electric service agreement at CLT-01 · May 27, 2026 · Primary
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (2)
Partially operational
65 MW
A 15-year electric-service agreement covers 65 MW of utility load.
Partially operational
Existing 34.5 kV onsite distribution can support the contracted utility load without major electrical upgrades.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.