Scope and capacity

Beyon Data Oasis is a 140,000-square-metre digital-infrastructure campus in southern Bahrain with data-center, solar and cable components.

Headline: See constituent sites

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project identity · Beyon Data Oasis

Source report · Beyon Data Oasis (Project)

Claim 132371 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Batelco by Beyon announces commissioning of Bahrain's first white-space data centre

    Beyon · Document date: Nov 2, 2025 · Primary

    Source reference: SRC-7058 · Government record · Recorded authority: Official primary

    Source URL

    https://beyon.com/2025/11/02/batelco-by-beyon-announces-commissioning-of-bahrains-first-white-space-data-centre-during-gateway-gulf-2025/

  2. Beyon announces the biggest ever investment in digital infrastructure in Bahrain

    Beyon · Document date: May 16, 2023 · Primary

    Source reference: SRC-7055 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.beyon.com/2023/05/16/beyon-announces-the-biggest-ever-investment-in-digital-infrastructure-in-bahrain/

Counterparties and capital