Bell AI Fabric Sherwood Data Center

Regina area, Saskatchewan, CanadaUnder construction
Evidence
Planned / design
300 MW
Updated
Oct 28, 2026

Bell is building a sovereign AI data center facility in the Rural Municipality of Sherwood, Saskatchewan. Bell states a 300 MW facility design and expects the first phase in the first half of 2027. Bell Canada, Bird Construction, George Gordon Developments is associated with the development in Regina area, Rural Municipality of Sherwood, SK, CA. The disclosed development scope includes 300 MW planned facility; construction partners appointed; first phase expected H1 2027. Power and physical infrastructure include sovereign AI infrastructure with Saskatchewan construction and site-services partners. Bell describes the Sherwood facility as a 300 MW data centre.

Capacity

Reported capacity

Planned / design or future potential

300 MW

Source

Reported capacity

Planned / design or future potential

300 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Construction programUnder construction

Project-wide phase for Bell AI Fabric Sherwood Data Center; capacity class is design.

Milestones (2)
Bell Saskatchewan AI Fabric development disclosed

May 14, 2026 · Recorded actual event

Completed · Announced

Source not linked
Construction partners appointed; first phase expected in H1 2027

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Bell Canada

Developer

Sources by role
Other participants (2)
Bird Construction

Contractor

Sources by role

Site & development

Location context

Actual

Bell AI Fabric facility | RM of Sherwood | Saskatchewan

Source

Location context

Actual

Bell AI Fabric facility | RM of Sherwood | Saskatchewan

Source

Development scale

Actual

300 MW planned facility

Source

Development milestone

Actual

Construction partners appointed

Source

Site configuration

Actual

Bell AI Fabric facility | RM of Sherwood | Saskatchewan

Source

Technical specifications

Power arrangement

Actual

First phase expected H1 2027.

Source

Additional project facts

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

Bell describes the Sherwood facility as a 300 MW data centre.

Source

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

Bell describes the Sherwood facility as a 300 MW data centre.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

300 MW

Bell describes the Sherwood facility as a 300 MW data centre.

Site facility

Planned or represented

Sovereign AI infrastructure with Saskatchewan construction and site-services partners.

Other · Documented