Cartis diligence evidence schedule
Bell AI Fabric Merritt
PRJ-0482 · Site · Merritt, British Columbia, Canada
Record last updated Oct 28, 2026
Scope and capacity
BCE's August 5, 2026 quarterly report expects the second phase of Merritt to enter service in early 2027. This is an expansion forecast, distinct from the first phase already in operation, with no additional operating MW inferred. Bell AI Fabric Merritt is a physical facility in Merritt, British Columbia. Bell's original 7 MW site plan and BUZZ HPC's immediate 6.5 MW gross allocation describe different scopes.
Headline: 7 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Original design capacity · 7 MW
Planned / design or future potential · Bell AI Fabric Merritt (Project)
Claim 45958 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Bell Canada Increases Sovereign AI Capacity with Bell AI Fabric
BCE / Bell Canada · Document date: May 28, 2025 · Primary
Source reference: SRC-2540
Source URL
https://www.bce.ca/Bell-Canada-Increases-Sovereign-AI-Capacity-with-Bell-AI-Fabric
https://www.bce.ca/Bell-Canada-Increases-Sovereign-AI-Capacity-with-Bell-AI-Fabric
Operating status · Live
Actual · Bell AI Fabric Merritt (Project)
Claim 45959 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BCE Q1 2026 financial reports and transcript
BCE · Document date: May 7, 2026 · Primary
Source reference: SRC-2544
Source URL
https://www.bce.ca/investors/financial-reports/quarterly-reports
https://www.bce.ca/investors/financial-reports/quarterly-reports
Launch timing · 2026-03-Late
Actual · Bell AI Fabric Merritt (Project)
Claim 45960 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BCE Q1 2026 financial reports and transcript
BCE · Document date: May 7, 2026 · Primary
Source reference: SRC-2544
Source URL
https://www.bce.ca/investors/financial-reports/quarterly-reports
https://www.bce.ca/investors/financial-reports/quarterly-reports
Buzz immediate gross allocation · 6.5 MW gross
Source report · Bell AI Fabric Merritt (Project)
Claim 45961 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- BUZZ HPC partnership advances sovereign accelerated GPU infrastructure in Merritt, B.C.
Bell Canada · Document date: Mar 25, 2026 · Primary
Source reference: SRC-2542
Source URL
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
- Bell Canada and BUZZ HPC partner at Bell AI Fabric facility in Merritt
BCE / Bell Canada · Document date: Mar 25, 2026 · Primary
Source reference: SRC-2543
Source URL
https://www.bce.ca/news-and-media/releases/show/bell-canada-and-buzz-hpc-partner-to-advance-sovereign-accelerated-gpu-infrastructure-at-bell-ai-fabr
https://www.bce.ca/news-and-media/releases/show/bell-canada-and-buzz-hpc-partner-to-advance-sovereign-accelerated-gpu-infrastructure-at-bell-ai-fabr
Buzz expansion option · True
Source report · Bell AI Fabric Merritt (Project)
Claim 45962 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- BUZZ HPC partnership advances sovereign accelerated GPU infrastructure in Merritt, B.C.
Bell Canada · Document date: Mar 25, 2026 · Primary
Source reference: SRC-2542
Source URL
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
Compute tenant · BUZZ HPC
Actual · Bell AI Fabric Merritt (Project)
Claim 45963 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BUZZ HPC partnership advances sovereign accelerated GPU infrastructure in Merritt, B.C.
Bell Canada · Document date: Mar 25, 2026 · Primary
Source reference: SRC-2542
Source URL
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
Compute hardware funder · Tenant
Actual · Bell AI Fabric Merritt (Project)
Claim 45964 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BCE Q1 2026 financial reports and transcript
BCE · Document date: May 7, 2026 · Primary
Source reference: SRC-2544
Source URL
https://www.bce.ca/investors/financial-reports/quarterly-reports
https://www.bce.ca/investors/financial-reports/quarterly-reports
Building power cooling provider · Bell
Actual · Bell AI Fabric Merritt (Project)
Claim 45965 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BCE Q1 2026 financial reports and transcript
BCE · Document date: May 7, 2026 · Primary
Source reference: SRC-2544
Source URL
https://www.bce.ca/investors/financial-reports/quarterly-reports
https://www.bce.ca/investors/financial-reports/quarterly-reports
Cooling type · Closed loop liquid cooling
Actual · Bell AI Fabric Merritt (Project)
Claim 45966 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BCE Q1 2026 financial reports and transcript
BCE · Document date: May 7, 2026 · Primary
Source reference: SRC-2544
Source URL
https://www.bce.ca/investors/financial-reports/quarterly-reports
https://www.bce.ca/investors/financial-reports/quarterly-reports
- BUZZ HPC partnership advances sovereign accelerated GPU infrastructure in Merritt, B.C.
Bell Canada · Document date: Mar 25, 2026 · Primary
Source reference: SRC-2542
Source URL
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
Municipal water draw for cooling · False
Source report · Bell AI Fabric Merritt (Project)
Claim 45967 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- BCE Q1 2026 financial reports and transcript
BCE · Document date: May 7, 2026 · Primary
Source reference: SRC-2544
Source URL
https://www.bce.ca/investors/financial-reports/quarterly-reports
https://www.bce.ca/investors/financial-reports/quarterly-reports
Workloads · AI inference and training
Actual · Bell AI Fabric Merritt (Project)
Claim 45968 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- BUZZ HPC partnership advances sovereign accelerated GPU infrastructure in Merritt, B.C.
Bell Canada · Document date: Mar 25, 2026 · Primary
Source reference: SRC-2542
Source URL
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
https://explore.business.bell.ca/artificial-intelligence-spotlight/buzz-hpc-partnership-advances-sovereign-accelerated-gpu-infrastructure-merritt-bc
Cohere hypertec buzz collaboration uses site · True
Source report · Bell AI Fabric Merritt (Project)
Claim 45969 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Bell AI Fabric, Cohere, Hypertec and BUZZ HPC announce landmark deal
BCE / Bell Canada · Document date: Jun 18, 2026 · Primary
Source reference: SRC-2546
Source URL
https://www.bce.ca/Bell-AI-Fabric-Cohere-Hypertec-and-BUZZ-HPC-announce-landmark-deal-to-advance-sovereign-AI-in-Canada
https://www.bce.ca/Bell-AI-Fabric-Cohere-Hypertec-and-BUZZ-HPC-announce-landmark-deal-to-advance-sovereign-AI-in-Canada
Counterparties and capital
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.