atNorth SWE02 Stockholm
Akalla / Kista, Stockholm, SwedenPreconstruction
Capacity
30 MW
Planned / design
Lead participant
atNorth
Developer
Last updated
Aug 26, 2026
Most recent public record update
About atNorth SWE02 Stockholm
atNorth's SWE02 facility in Akalla has a granted building permit and is designed for 30 MW of site power capacity, with Q4 2027 still presented as its go-live target.
Capacity
Planned / designOperating capacity—An operating IT-capacity figure has not been publicly disclosed.
Design30 MWForecast · atNorth SWE02 Stockholm
Development
2 phases · 3 milestonesSWE02 permitting and consultationAnnounced Or Preconstruction
Akalla 4:8 facility; no achieved construction start found.
1 building
SWE02 planned full facilityPlanned
Targets and design specifications only.
1 building
Oct 1, 2025
Stockholm grants SWE02 building permit
CompletedJan 14, 2026
atNorth updates SWE02 consultation package
CompletedOct 1, 2027
SWE02 target go-live
ForecastInfrastructure
Electric GridPlanned Or Represented
30 MW
Operator labels this site power capacity, not IT load.
Onsite GenerationPlanned Or Represented
100 MW thermal input
Aggregate installed combustion input for 12 generators; not site power or IT load.
Electric GridPlanned Or Represented
New Ellevio substation described in consultation material; energization unverified.
Cooling SystemPlanned Or Represented
DLC-ready white space with chilled-water/mechanical primary cooling.
Heat ReusePlanned Or Represented
Future heat capture and district-network delivery; not operating.
Project map
0 of 1 project point mappedInfrastructure facts
5
Mapped records
1
Capacity figures
2
No map point available
Power & interconnection: 2Generation & storage: 1Cooling & water: 2
Facts & sources
Published claims and their source links.
Current StatusPermitted; construction start unverifiedActual
Permitted; construction start unverified
Building PermitGranted October 2025Permitted
Granted October 2025
Site Power Capacity30 MWForecast
30 MW
Facility Size15,000 square metresActual
15,000 square metres
Property Area1.5 hectaresActual
1.5 hectares
Target RfsQ4 2027Forecast
Q4 2027
Pue Target≤1.2Design
≤1.2
Heat ReusePlanned with Stockholm ExergiForecast
Planned with Stockholm Exergi
CoolingChilled water, mechanical free cooling and DLC-ready whitespaceDesign
Chilled water, mechanical free cooling and DLC-ready whitespace
Rack DensityAverage 40; liquid cooled 100+ kW per rackDesign
Average 40; liquid cooled 100+ kW per rack
New SubstationPlanned by EllevioForecast
Planned by Ellevio