atNorth SWE01 Stockholm Data Center Campus

Kista, Stockholm County, SwedenPartially operational
Evidence
Planned / design
12 MW
Updated
Oct 28, 2026

atNorth SWE01 Stockholm Data Center Campus, also known as atNorth SWE01, is a data center project in Kista, Stockholm County, SE associated with atNorth. 6,400-square-metre facility; 12 MW published site power capacity; operating high-density metro site. Renewable-energy Stockholm campus with direct liquid cooling and district heat recovery.

Capacity

Reported capacity

Planned / design or future potential

12 MW

Source

Reported capacity

Planned / design or future potential

12 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionPartially operational

12 MW is the operator-published facility or campus design boundary.

Participants

atNorth

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

AtNorth SWE01 | Kista | Stockholm County | SE

Source

Location context

Actual

AtNorth SWE01 | Kista | Stockholm County | SE

Source

Location context

Actual

Kista, Stockholm County, SE

Source

Development detail

Actual

6,400-Square metre facility; 12 MW published site power capacity; operating high density metro site.

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

AtNorth publishes 12 MW of site power capacity for SWE01; Cartis does not equate it with measured IT load.

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

12 MW facility or campus design capacity.

Source

Project identity

Actual

AtNorth SWE01

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

12 MW facility or campus design capacity.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Energized

Renewable-energy Stockholm campus with direct liquid cooling and district heat recovery.

Cooling system

Operational

Cooling and efficiency claims remain limited to operator-described designs; no water use or delivered load is inferred.

Public-source research. Plans may change. See Evidence for sources and qualifications.