Skip to content

atNorth Solleftea SWE04 Mega Campus

Langsele, Solleftea, Vasternorrland, SwedenPreconstruction
Evidence
Planned / design
300 MW
Updated
Oct 28, 2026

atNorth plans a 300 MW mega campus at the fully zoned Hamre 1 site in Langsele, targeting H1 2028. atNorth Solleftea SWE04 Mega Campus is located in Langsele, Solleftea, Vasternorrland, SE and is a data center campus in preconstruction status.

Capacity

Planned site power capacity

Planned / design or future potential

300 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Original initial conceptAnnounced or preconstruction

Superseded by 2026 300 MW / 50-hectare disclosure.

SWE04 campus buildoutAnnounced or preconstruction

Site-power envelope; committed construction phases are undisclosed.

Milestones (4)
atNorth announced initial Solleftea land agreement

Dec 16, 2024 · Recorded actual event

Completed · Event type not stated

Source not linked
Municipality reports signed purchase agreement and final detailed plan

2026 · Recorded actual event

Completed · Event type not stated

Source not linked
atNorth confirmed SWE04 plan

Feb 23, 2026 · Recorded actual event

Completed · Announced

Source not linked
Campus targeted for H1 2028

2028 · Forecast / planned record

Forecast · Event type not stated

Source not linked

Participants

atNorth

Developer · Operator

Sources by role
Developer / Operator (1)
Developer (1)
Solleftea Municipality

Government authority · Landowner

Sources by role
Government authority (1)
Government authority (1)
Landowner (1)
Landowner (1)

Site & development

Current site area approximately

Actual

50 hectares

Source

Land purchase agreement signed

Actual

True

Source

Land price

Actual

175 SEK million

Source

Technical specifications

Renewable energy design

Actual

True

Source

Direct liquid cooling ready

Actual

True

Source

Additional project facts

Target operational period

Actual

H1 2028

Source

Detailed plan final

Actual

True

Source

Planned direct jobs low

Actual

100 jobs

Source

Planned direct jobs high

Actual

150 jobs

Source

Design PUE

Actual

1.2

Source

Waste heat reuse planned

Actual

True

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

Heat reuse

Planned or represented

atNorth will pursue local heat-reuse partnerships; none is disclosed as contracted or operating.

Permit · Status not stated

SWE04 / Hamre 1

Solleftea Municipality

Jan 1, 2026

Sources (1)