Skip to content
All records
Data center siteSite record

atNorth FIN04 Myllykoski Mega Data Center Campus

Kouvola, Kymenlaakso, FinlandUnder construction
Capacity
430 MW
Planned / design
Lead participant
atNorth
Developer
Last updated
Aug 28, 2026
Most recent public record update

About atNorth FIN04 Myllykoski Mega Data Center Campus

atNorth FIN04 Myllykoski Mega Data Center Campus, also known as atNorth FIN04, is a data center project in Kouvola, Kymenlaakso, FI associated with atNorth. 45-hectare greenfield campus; 430 MW published campus power capacity; first operations targeted for 2026. Renewable-energy mega campus designed for high-density workloads, liquid cooling and municipal heat reuse. 430 MW is the source-defined future IT or site design envelope.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential430 MWDesign · atNorth FIN04 Myllykoski Mega Data Center Campus
Future Potential430 MWDesign · atNorth FIN04 Myllykoski Mega Data Center Campus

Development

1 phases · 2 milestones
Development, permitting and phased deliveryUnder Construction

430 MW is the source-defined future IT or site design envelope. It is not operating IT load.

May 16, 2024
atNorth announced FIN04 at Myllykoski
Completed
Jun 30, 2026
Current project page targets first availability in first half 2026
Forecast

Infrastructure

Electric GridPlanned Or Represented

Renewable-energy mega campus designed for high-density workloads, liquid cooling and municipal heat reuse.

Cooling SystemPlanned Or Represented

Cooling and efficiency claims remain limited to operator-described designs; no water use or delivered load is inferred.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
AtNorth FIN04 | Kouvola | Kymenlaakso | FI
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
430 MW
Design
Capacity Basis
AtNorth publishes 430 MW of campus power capacity for FIN04; Cartis does not equate it with operating IT load.
Actual
Location Context
AtNorth FIN04 | Kouvola | Kymenlaakso | FI
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
430 MW
Design
Capacity Basis
430 MW is the source defined future IT or site design envelope.
Actual
Project Identity
AtNorth FIN04
Actual
Location Context
Kouvola, Kymenlaakso, FI
Actual
Lifecycle Status
Construction
Actual
Development Detail
45-Hectare greenfield campus; 430 MW published campus power capacity; first operations targeted for 2026.
Actual
Capacity Basis
430 MW is the source defined future IT or site design envelope.
Actual