Cartis diligence evidence schedule

AtlasEdge VIE001 Vienna Data Center

PRJ-1041 · Site · Vienna, Austria

Record last updated Oct 28, 2026

Scope and capacity

VIE001 is AtlasEdge’s operating Siemens Campus facility. The profile preserves the current 1.6 MW site-utility boundary and treats the separate 10 MW acquisition-era expansion concept as future campus context, avoiding a false operating-capacity uplift. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Headline: 1.6 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · VIE001 | Vienna | Vienna | AT

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 68111 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Lifecycle status · Operating

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 68112 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Reported capacity · 1.6 MW

Design · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 68113 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Capacity basis · AtlasEdge publishes 1.6 MW for VIE001.

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 68114 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Location context · VIE001 | Vienna | Vienna | AT

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81118 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Lifecycle status · Operating

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81119 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Reported capacity · 1.6 MW

Design · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81120 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Capacity basis · 1.6 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81121 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Operator confirmed · AtlasEdge

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81122 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Facility capacity basis · 1.6 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81123 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Current lifecycle · Operating

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81124 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Operating model · Carrier neutral colocation

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81126 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Renewable energy claim · 100 percent

Actual · AtlasEdge VIE001 Vienna Data Center (Project)

Claim 81127 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AtlasEdge VIE001 Vienna Data Center official profile

    AtlasEdge · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3895 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://atlasedge.com/data-centres/vienna/

Counterparties and capital

AtlasEdge · Developer · CMP-1487

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.