Skip to content
← Return to profile

Cartis diligence evidence schedule

AtlasEdge LIS001 Lisbon Data Center

PRJ-1038 · Site · Lisbon, Lisbon District, Portugal

Captured 2026-09-06T04:13:20.398Z · Record last updated 2026-08-28

SHA-256: 5ad3ff34dc3cf7547ce9db992f1513386df25a76c7a2462fb70658327d61c76d

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

AtlasEdge LIS001 Lisbon Data Center is part of AtlasEdge’s three-phase Lisbon campus near the Carcavelos cable-landing corridor. The current facility capacity is kept separate from the 30 MW campus program. A €253 million sustainability-linked facility funds LIS001 and LIS002, with project-specific tranches recorded rather than attributed as standalone facility value. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Headline: 5.1 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Location Context · LIS001 | Lisbon | Lisbon District | PT

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 68099 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Lifecycle Status · Operating

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 68100 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Reported Capacity · 5.1 MW

design · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 68101 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Capacity Basis · AtlasEdge publishes 5.1 MW for LIS001.

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 68102 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Location Context · LIS001 | Lisbon | Lisbon District | PT

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81084 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Lifecycle Status · Operating

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81085 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Reported Capacity · 5.1 MW

design · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81086 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Capacity Basis · 5.1 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81087 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Operator Confirmed · AtlasEdge

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81088 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Facility Capacity Basis · 5.1 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81089 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Current Lifecycle · Operating

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81090 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Operating Model · Carrier neutral colocation

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81092 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Renewable Energy Claim · 100 percent

actual · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81093 · Review: Approved · Claim date: Not published

  1. AtlasEdge LIS001 Lisbon Data Center official profile

    AtlasEdge · Document date: 2026-08-28 · Primary

    https://atlasedge.com/data-centres/Lisbon/

Campus Green Financing · €253,000,000

closed financing · AtlasEdge LIS001 Lisbon Data Center (project)

Claim 81094 · Review: Approved · Claim date: Not published

  1. €253 million Lisbon campus green financing

    AtlasEdge · Document date: 2025-10-28 · Primary

    https://atlasedge.com/atlasedge-secures-e253-million-in-green-financing-for-lisbon-campus-expansion/

Counterparties and capital

AtlasEdge · Developer · CMP-1487

Debt Financing

€253,000,000 · 2025-10-28

Shared LIS001/LIS002 campus financing; Facility A €63m and Facility B €190m.

AtlasEdge (Borrower)

Financing record 175; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.