Scope and capacity

Vinhedo 3 is a 90 MW AI-focused facility under construction on the existing campus.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project identity · Ascenty Vinhedo 3

Source report · Ascenty Vinhedo 3 (Project)

Claim 132386 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Ascenty secures 150 MW of new AI contracts

    Ascenty · Document date: May 28, 2026 · Primary

    Source reference: SRC-7030 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ascenty.com/en/blog/news-ascenty-en/ascenty-ai-contracts/

Counterparties and capital

Ascenty · Operator · CMP-1227

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.