Ascenty Vinhedo 2
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
Vinhedo 2 has operated since 2020. Its current product page lists 34 MW of site power, while a later expansion announcement describes an increase from 50 MW to 80 MW under a different scope.
Program relationships
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Current product page says 34 MW; later expansion release uses a 50 MW starting figure.
1 building
Capacity-definition reconciliation remains open.
Milestones (1)
2020 · Recorded actual event
Completed · Commercial operation
Source not linkedParticipants
Additional project facts
Infrastructure & permits
Technical details (1)
Planned or represented
80 MW
The 80 MW figure applies to a later expansion release and is distinct from the 34 MW product-page figure.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (3)
Operating · Avenida Joao Batista Nunes 50, Vinhedo, São Paulo, Brazil
Same locality: Avenida Joao Batista Nunes 50, Vinhedo · Shared participant: Ascenty
Compare in a collectionStatus under review · Greater São Paulo, São Paulo, Brazil
Shared participant: Ascenty · Same market: São Paulo, Brazil
Compare in a collectionUnder construction · Vinhedo campus, São Paulo, Brazil
Shared participant: Ascenty · Same market: São Paulo, Brazil
Compare in a collection