PRJ-0541 · Site · Avenida Joao Batista Nunes 50, Vinhedo, São Paulo, Brazil

Record last updated Oct 28, 2026

Scope and capacity

Vinhedo 1 has operated since 2019 and is listed at 27 MW site power, 21,000 sqm and 3,300 racks.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project identity · Ascenty Vinhedo 1

Source report · Ascenty Vinhedo 1 (Project)

Claim 132384 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Data Center Vinhedo 1

    Ascenty · Document date: Not stated · Primary

    Source reference: SRC-7095 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://ascenty.com/en/data-centers-en/location/brazil/sao-paulo-interior-campus/vinhedo/vinhedo-1/

  2. The Largest Data Center in Brazil and Latin America Is in Vinhedo

    Ascenty · Document date: Jan 27, 2026 · Primary

    Source reference: SRC-7097 · Company announcement · Recorded authority: Party primary

    Source URL

    https://ascenty.com/en/blog/articles/the-largest-data-center-in-brazil-and-latin-america-is-in-vinhedo/

Counterparties and capital

Ascenty · Operator · CMP-1227

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.