Ascenty SPO05

Greater São Paulo, SP, BrazilOperating / Stabilized
Capacity
No public figure
Lead participant
No public role record
Last updated
Aug 26, 2026
Most recent public record update

About Ascenty SPO05

SPO05 began operations in May 2026 and represents a reported R$300 million investment on Ascenty's existing Greater São Paulo campus.

Program relationships

1 linked

Projects sharing a market, utility, or organization.

1 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

1 phases · 2 milestones
SPO05 deliveryOperational

Operating from May 2026.

1 building

Jul 3, 2025
SPO05 construction announced
Completed
May 8, 2026
SPO05 enters operation
Completed

Infrastructure

No public infrastructure records are attached.

Project map

0 of 1 project point mapped
Infrastructure facts
0
Mapped records
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

2 facts
Milestone Announcement
SPO05 construction announced
Actual
Milestone Ready For Service
SPO05 enters operation
Actual