AQ Compute BCN1 Barcelona Data Center Campus

Cerdanyola del Vallès, Catalonia, SpainUnder construction
Evidence
Planned critical IT
60 MW
Updated
Oct 28, 2026

AQ-BCN1 is a multi-building campus in Parc de l’Alba. Public material separates the initial 15 MW building from a 60 MW campus design and discusses renewable-energy and liquid-cooling objectives; neither number is current operating utilization. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Capacity

Reported capacity

Design

60 MW

Source

Reported capacity

Planned / design or future potential

60 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development, permitting and phased deliveryAnnounced or preconstruction

AQ-BCN1 is a multi-building campus in Parc de l’Alba. Public material separates the initial 15 MW building from a 60 MW campus design and discusses renewable-energy and liquid-cooling objectives; neither number is current operating utilization. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Milestones (1)
City and developer marked the start of construction

Mar 14, 2024 · Recorded actual event

Completed · Construction started

Source not linked

Participants

AQ Compute

Developer

Sources by role

Site & development

Location context

Actual

AQ-BCN1 | Cerdanyola del Vallès | Catalonia | ES

Source

Location context

Actual

AQ-BCN1 | Cerdanyola del Vallès | Catalonia | ES

Source

Technical specifications

Renewable energy target

Forecast

100 percent

Source

Additional project facts

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

AQ Compute publishes 60 MW for the full AQ-BCN1 campus boundary.

Source

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

60 MW is a published future facility or full build IT boundary; it is not operating load.

Source

Operator confirmed

Actual

AQ Compute

Source

Facility capacity basis

Actual

60 MW is a published future facility or full build IT boundary; it is not operating load.

Source

Current lifecycle

Actual

Under development

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

60 MW

Published IT design boundary; utility service and operating load remain distinct.

Fiber

Planned or represented

Carrier-neutral or resilient fibre connectivity described for the individual facility.

Other · Issued

AQ-BCN1

City of Cerdanyola del Vallès

Mar 14, 2024

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.