Applied Digital Jamestown Data Center
- Facility design
- 106 MW
- Updated
- Oct 28, 2026
Applied Digital’s Jamestown facility is a 106 MW operating hosting data center in Stutsman County, North Dakota. The company reported that the facility was operating at full capacity by May 2025. A smaller adjacent high-performance-computing installation is distinct from the 106 MW blockchain-hosting facility and is not added to its capacity headline.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Operating at full facility capacity by May 2025.
Smaller adjacent HPC deployment with a separate electrical boundary.
Milestones (1)
May 31, 2025 · Recorded actual event
Completed · Capacity revised
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- Applied Digital 2025 Form 10-K · Aug 29, 2025 · Primary
Operator (1)
- Applied Digital fiscal 2025 results · Jul 30, 2025 · Corroborating
Infrastructure & permits
Technical details (1)
Operational
106 MW
Electrical design of the primary hosting facility.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.