Cartis diligence evidence schedule

Apple Valley Technology Park Data Center Proposal

PRJ-0588 · Site · Apple Valley, Minnesota, United States

Record last updated Oct 28, 2026

Scope and capacity

Apple Valley denied the core land-use requests for Oppidan's proposed technology park in early 2026 after the property owner withdrew consent for rezoning.

Headline: 250–300 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Current status · Denied and cancelled

Actual · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53305 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Corroborating

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

  2. City Council denies Technology Park comprehensive plan amendments

    City of Apple Valley · Document date: Jan 23, 2026 · Corroborating

    Source reference: SRC-2877 · Government record · Recorded authority: Official primary

    Source URL

    https://www.applevalleymn.gov/CivicAlerts.aspx?AID=4155&ARC=6287

  3. Proposed Technology Park

    City of Apple Valley · Document date: Not stated · Primary

    Source reference: SRC-2876 · Government record · Recorded authority: Official primary

    Source URL

    https://www.cityofapplevalley.org/1024/13898/Proposed-Technology-Park

Site address · 15255 Johnny Cake Ridge Road

Actual · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53306 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Proposed Technology Park

    City of Apple Valley · Document date: Not stated · Primary

    Source reference: SRC-2876 · Government record · Recorded authority: Official primary

    Source URL

    https://www.cityofapplevalley.org/1024/13898/Proposed-Technology-Park

Site area · 134 acres

Proposal · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53307 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Corroborating

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

  2. Proposed Technology Park

    City of Apple Valley · Document date: Not stated · Primary

    Source reference: SRC-2876 · Government record · Recorded authority: Official primary

    Source URL

    https://www.cityofapplevalley.org/1024/13898/Proposed-Technology-Park

Total building count · 7 buildings

Proposal · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53308 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

  1. Proposed Technology Park

    City of Apple Valley · Document date: Not stated · Primary

    Source reference: SRC-2876 · Government record · Recorded authority: Official primary

    Source URL

    https://www.cityofapplevalley.org/1024/13898/Proposed-Technology-Park

Data center building count · 5 buildings

Proposal · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53309 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

  1. Proposed Technology Park

    City of Apple Valley · Document date: Not stated · Primary

    Source reference: SRC-2876 · Government record · Recorded authority: Official primary

    Source URL

    https://www.cityofapplevalley.org/1024/13898/Proposed-Technology-Park

Gross floor area · 1,050,000 square feet

Reported rounded · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53310 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Primary

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

Proposed capacity range · 250–300 MW

Planned / design or future potential · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53311 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Primary

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

Comprehensive plan amendments · Denied 2026-01-22

Actual · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53312 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City Council denies Technology Park comprehensive plan amendments

    City of Apple Valley · Document date: Jan 23, 2026 · Primary

    Source reference: SRC-2877 · Government record · Recorded authority: Official primary

    Source URL

    https://www.applevalleymn.gov/CivicAlerts.aspx?AID=4155&ARC=6287

Rezoning · Withdrawn 2026-03-06

Actual · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53313 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Primary

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

Conditional use permit · Denied 2026-03-26

Actual · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53314 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Primary

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

Construction status · Never started

Actual · Apple Valley Technology Park Data Center Proposal (Project)

Claim 53315 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Oppidan data center outside Minneapolis rejected

    Data Center Dynamics · Document date: Mar 30, 2026 · Corroborating

    Source reference: SRC-2878 · Government record · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/oppidan-data-center-outside-minneapolis-rejected/

  2. Proposed Technology Park

    City of Apple Valley · Document date: Not stated · Primary

    Source reference: SRC-2876 · Government record · Recorded authority: Official primary

    Source URL

    https://www.cityofapplevalley.org/1024/13898/Proposed-Technology-Park

Counterparties and capital

City of Apple Valley · Government authority · CMP-1365

Oppidan Investment Company · Developer · CMP-1363

Rockport LLC · Owner · CMP-1364

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.