Anan Afula Data Center

Afula, Z, IsraelUnder construction
Evidence
Planned critical IT
100 MW
Updated
Oct 28, 2026

Anan Afula Data Center is one physical Afula facility. Crusoe's 40 MW long-term allocation is a customer commitment within the site, part of the same site; historical 64/80 MW and current approximately 100 MW site scopes remain time-labeled.

Capacity

Current expected site capacity

Actual

100 MW

Source

Crusoe capacity allocation

Planned / design or future potential

40 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Afula buildoutUnder construction

1 building

Approximately 100 MW current site expectation; allocation and historical designs remain separated.

Milestones (2)
Anan–Crusoe 40 MW agreement reported

Apr 26, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
Afula confirmed under construction

Apr 28, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked

Participants

Anan Data Centers

Operator

Sources by role
Lian Group / Nissim Shriel-Gaon

Investor

Sources by role
Investor (1)
Investor (1)
Maor Maloul

Investor

Sources by role
Investor (1)
Investor (1)
Omer Adam

Investor

Sources by role
Investor (1)
Investor (1)
Other participants (1)

Capital & incentives

Financing records

Reported company bank loan

₪420,000,000

Jan 1, 2024

Reported company bank loan for Anan's buildout; the amount is not allocated specifically to Afula.

Parties & sources

Anan Data Centers (Borrower) · Mizrahi Tefahot Bank (Lender)

Reported founder equity

₪200,000,000

Jan 1, 2024

Reported founder equity for Anan; the amount is not allocated specifically to Afula.

Parties & sources

Anan Data Centers (Equity recipient)

Company minority stake transaction

Amount not disclosed

Nov 1, 2025

Battery Global Advisors reported purchase of 20% of Anan at NIS1bn valuation; not project debt or Crusoe contract value. The disclosed value is a 20 percent stake, not a currency amount; canonical financing amount is intentionally blank. Percent stake is not an ISO currency; canonical currency is intentionally blank.

Parties & sources

Anan Data Centers (Investee company) · Battery Global Advisors (Minority investor)

Site & development

Building area

Source report

30,000 square metres

Source

Construction status

Actual

Under construction

Source

Reported site area

Source report

200 dunams

Source

Additional project facts

Contract expansion option

Source report

True

Source

Underground floor count

Source report

1 floor

Source

Above ground storey count

Source report

3 storeys

Source

Tzora included in boundary

Source report

False

Source

Infrastructure & permits

Technical details (2)
Electric grid

Under construction

100 MW approximate site design

Current expected site scope; utility contract and energization schedule not public.

Compute and platform system

Secured or contracted

40 MW customer allocation

Long-term allocation within Afula, not a separate facility or verified live load.

Public-source research. Plans may change. See Evidence for sources and qualifications.