Cartis diligence evidence schedule

Aligned Project Caprock Campus

PRJ-0475 · Site · Abernathy, Texas, United States

Captured 2026-09-06T04:12:22.307Z · Record last updated 2026-08-25

SHA-256: 17ed3eadb0ac55f6497ee7061b6c1af978664d6ff57ed7d997f939417c0cfe6a

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

313-acre campus boundary covering six planned facilities and shared utility infrastructure. The 540 MW figure is a campus design envelope, not publicly disclosed operating IT load.

Headline: 540 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Site Area · 313 acres

Source report · Aligned Project Caprock Campus (project)

Claim 45867 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Physical Facility Count · 6 facilities

Source report · Aligned Project Caprock Campus (project)

Claim 45868 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Planned Gross Building Area · 1,650,000 square feet

Planned / design or future potential · Aligned Project Caprock Campus (project)

Claim 45869 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Campus Design Capacity · 540 MW

Planned / design or future potential · Aligned Project Caprock Campus (project)

Claim 45870 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. Aligned breaks ground on 540MW data center campus in Texas

    Data Center Dynamics · Document date: 2026-04-10 · Primary

    https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-540mw-data-center-campus-in-texas/
  2. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Construction Started · 2026-04-09

actual · Aligned Project Caprock Campus (project)

Claim 45871 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

First Facility Service Target · 2027-Q1

Planned / design or future potential · Aligned Project Caprock Campus (project)

Claim 45872 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Expected Regional Economic Injection · $5 billion

Source report · Aligned Project Caprock Campus (project)

Claim 45873 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Construction Jobs · Thousands

actual · Aligned Project Caprock Campus (project)

Claim 45874 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Utility Partner · Xcel Energy

actual · Aligned Project Caprock Campus (project)

Claim 45875 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Dedicated Electrical Infrastructure Funded By Sponsor · True

Source report · Aligned Project Caprock Campus (project)

Claim 45876 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Liquid Cooling Platform · DeltaFlow

actual · Aligned Project Caprock Campus (project)

Claim 45877 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Closed Loop Water Design · True

Source report · Aligned Project Caprock Campus (project)

Claim 45878 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Air Cooled Heat Rejection · True

Source report · Aligned Project Caprock Campus (project)

Claim 45879 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Aquifer Protection Claim · Ogallala Aquifer

actual · Aligned Project Caprock Campus (project)

Claim 45880 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Construction Partner · Ryan Companies

actual · Aligned Project Caprock Campus (project)

Claim 45881 · Review: Approved · Claim date: Not published

  1. Aligned Breaks Ground on Project Caprock

    Aligned Data Centers · Document date: 2026-04-09 · Primary

    https://aligneddc.com/press-release/aligned-breaks-ground-on-project-caprock/

Current Platform Acquisition Sponsors · AIP; MGX; BlackRock GIP

actual · Aligned Project Caprock Campus (project)

Claim 45883 · Review: Approved · Claim date: Not published

  1. AIP, MGX and BlackRock's GIP close acquisition of Aligned Data Centers

    Aligned Data Centers · Document date: 2026-07-21 · Primary

    https://aligneddc.com/press-release/aip-mgx-and-blackrocks-gip-close-acquisition-of-aligned-data-centers/

Counterparties and capital

Aligned Data Centers · Operator · CMP-0165

Macquarie Asset Management · Owner · CMP-1169

Ryan Companies · Contractor · CMP-1167

Xcel Energy · Utility Provider · CMP-0437

Platform Acquisition Enterprise Value

$40,000,000,000 · 2026-07-21

AIP/MGX/BlackRock GIP acquisition of 100% of Aligned; no Caprock allocation and not project debt.

Artificial Intelligence Infrastructure Partnership (Acquisition Sponsor) · BlackRock Global Infrastructure Partners (Acquisition Sponsor) · Macquarie Asset Management (Seller / Former Owner) · MGX (Acquisition Sponsor)

Financing record 135; claim-specific source links appear in the exhibit sources where published.

Platform Growth Capital

$5,000,000,000 · 2026-07-21

Additional capital committed to Aligned after acquisition; no Caprock allocation.

Artificial Intelligence Infrastructure Partnership (Growth Capital Sponsor) · BlackRock Global Infrastructure Partners (Growth Capital Sponsor) · MGX (Growth Capital Sponsor)

Financing record 136; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.