Aligned LBB-01

Abernathy, Texas, United StatesUnder construction
Evidence
Planned / design
2 MW
Updated
Oct 28, 2026

Aligned LBB-01 is the first named physical facility within Project Caprock. TDLR registration scope, cost, dates and area attach only to LBB-01, not the full campus.

Capacity

UPS lineup capacity

Planned / design or future potential

2 MW

Source

Critical distribution capacity

Planned / design or future potential

1 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

LBB-01 constructionUnder construction

1 building

TDLR dates and cost attach to this facility only.

Milestones (3)
TDLR registered start

Apr 24, 2026 · Event timing type not established

Status not stated · Construction started

Source not linked
Aligned LBB-01 service target

Q1 2027 · Forecast / planned record

Forecast · Event type not stated

Source not linked
TDLR registered completion

Nov 15, 2027 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

No participants published.

Capital & incentives

Capital claims

Registered estimated cost

Source report

$425 million

Source

Site & development

Registered project area

Source report

190,694 square feet

Source

Registered completion date

Actual

2027-11-15

Source

Technical specifications

Rack voltage

Source report

415 V

Source

Additional project facts

Facility identifier

Actual

LBB-01

Source

Public address

Actual

1498 County Road 315, Abernathy, TX

Source

Regulatory project address

Actual

1421 FM 54, Hale County, TX

Source

Registered start date

Actual

2026-04-24

Source

Legal owner

Actual

Aligned Data Centers (Abernathy) Propco LLC

Source

Design firm

Actual

Corgan

Source

Tenant identity

Actual

Not assigned / undisclosed

Source

Redundancy

Actual

N+1 block redundant

Source

Service level uptime

Source report

100 percent

Source

Infrastructure & permits

Technical details (1)
Electric grid

Planned or represented

2 MW UPS lineups

N+1 block redundant electrical design; 1 MW CDPs and 415 V rack distribution.

Permit · Status not stated

ADC-LBB01

Texas Department of Licensing and Regulation

Jun 23, 2026

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.