Cartis diligence evidence schedule

1547 Chester County Data Center Campus

PRJ-1167 · Site · Chester County, Pennsylvania, United States

Record last updated Oct 28, 2026

Scope and capacity

1547’s Chester County, Pennsylvania powered-land site spans about 100 acres with zoning for two roughly one-million-square-foot data-center buildings. PECO’s commitment increased from an initial 290 MW to at least 450 MW, and 1547 now marks the land as sold; the current owner and delivery schedule are not publicly disclosed.

Headline: 450 MW Contracted

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · 1547 Chester County Data Center Campus | Chester County | Pennsylvania | US

Actual · 1547 Chester County Data Center Campus (Project)

Claim 71990 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Lifecycle status · Proposed

Actual · 1547 Chester County Data Center Campus (Project)

Claim 71991 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Reported capacity · 450 MW

Actual · 1547 Chester County Data Center Campus (Project)

Claim 71992 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Capacity basis · 450 MW contracted power supply; not measured operating IT load. The 450 MW value is a minimum utility delivery commitment, not operating IT load.

Actual · 1547 Chester County Data Center Campus (Project)

Claim 71993 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Site area · 100 acres

Actual · 1547 Chester County Data Center Campus (Project)

Claim 77988 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Building count · 2 buildings

Actual · 1547 Chester County Data Center Campus (Project)

Claim 77989 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Gross floor area · 2,000,000 square feet

Design · 1547 Chester County Data Center Campus (Project)

Claim 77990 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Ownership status · Sold

Actual · 1547 Chester County Data Center Campus (Project)

Claim 77991 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 1547 Chester County Data Center Campus project source

    1547 Critical Systems Realty · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4156 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.1547realty.com/data-centers/

Counterparties and capital

1547 Critical Systems Realty · Developer · CMP-1542