Shared developer: Amazon Web ServicesSame market: Indiana, United States
All records
Data center siteSite record
AWS New Carlisle / Project Rainier Indiana
New Carlisle, St. Joseph County, Indiana, United StatesExpanding
Capacity
—
No public figure
Lead participant
Amazon Web Services
Campus Developer Operator And Compute Provider
Last updated
Oct 29, 2025
Most recent public record update
About AWS New Carlisle / Project Rainier Indiana
AWS's New Carlisle campus is the anchor physical site associated with Project Rainier, a distributed Trainium2 compute cluster for Anthropic. AWS announced an $11 billion Indiana investment; Rainier became fully operational in 2025 with nearly half a million Trainium2 chips across multiple U.S. data centers.
Related projects
Projects sharing a market, utility, or organization.
Site · Shared context
AWS Project Rainier — St. Joseph County Site
Partially operational · New Carlisle area, Indiana, United States
Shared developer: Amazon Web ServicesSame market: Indiana, United States
Capacity
Operating capacity—An operating IT-capacity figure has not been publicly disclosed.
No additional capacity claims are published.
Development
2 phases · 0 milestonesInitial New Carlisle campus buildOperational And Expanding
Distributed Rainier Trainium2 clusterOperational
Infrastructure
Cooling No Water MonthsDesign
October through March
Aws Water Use EfficiencyFleet Metric Not Site Specific
0.15 liters/kWh
Project map
0 of 1 project point mappedInfrastructure facts
2
Mapped records
1
Capacity figures
1
No map point available
Cooling & water: 2
Facts & sources
Published claims and their source links.
Indiana Investment$11,000,000,000Announced
$11,000,000,000
Minimum New Jobs1,000 jobsCommitted
1,000 jobs
Data Center Sales Tax Exemption Term50 yearsIncentive
50 years
Headcount Tax Credits$18,300,000Performance Based Maximum
$18,300,000
Training Grants$5,000,000Performance Based Maximum
$5,000,000
Hoosier Business Investment Credits$55,000,000Performance Based Maximum
$55,000,000
Redevelopment Tax Credits$20,000,000Performance Based Maximum
$20,000,000
Road Contribution$7,000,000Committed Maximum
$7,000,000
Rainier Chip CountNearly 500000 Trainium2 chipsActual Company Reported
Nearly 500000 Trainium2 chips
Rainier StatusFully operational statusActual Company Reported
Fully operational status
Rainier GeographyMultiple U.S. data centers scopeActual Company Reported
Multiple U.S. data centers scope
Cooling No Water MonthsOctober through March monthsDesign
October through March months
Aws Water Use Efficiency0.15 liters/kWhFleet Metric Not Site Specific